Llwyn-On Reservoir Scour Valve Refurbishment

机译:Llwyn-On水库冲刷气门翻新

获取原文
获取原文并翻译 | 示例

摘要

This paper has been prepared as a case study looking at the refurbishment of critical valves that had previously been declared to be beyond economical repair. It describes the inspection and repair of two 900mm diameter Larner Johnson valves installed some 80 years ago. There were considerable challenges in gaining safe access to enable the valves to be removed from the outlet tunnel and taken back to the factory for refurbishment. Once the valves had been removed the gears and plunger were refurbished, bronze liners were cast and fitted, all iron surfaces were coated with epoxy paint and all bolts were replaced with stainless steel ones. The valves were successfully reinstalled and commissioned.
机译:本文是作为案例研究准备的,目的是研究以前被宣布无法进行经济维修的关键阀门的整修。它描述了大约80年前安装的两个900mm直径Larner Johnson阀门的检查和维修。在获得安全通道以将阀门从出口隧道中取出并送回工厂进行翻新方面,存在着巨大的挑战。卸下阀门后,对齿轮和柱塞进行翻新,铸造和安装青铜衬套,所有铁表面均涂上环氧涂料,所有螺栓均替换为不锈钢。阀门已成功重新安装并调试。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号