The Zone 4 Feedermain Project involves the installation of approximately 13,000m of trunk watermain from Trafalgar Road and Britannia Road to the Zone 4 Reservoir near Trafalgar Road and No.5 Side Road. The watermain was designed to be installed by both open cut and trenchless methodologies and includes 3,100m of 1200mm diameter feedermain, 7,070m of twin 900mm diameter feedermain and 2,800m of single 900mm feedermain. 4,080m of the watermains is to be installed by trenchless methods with tunnel diameters ranging from 1,800mm to 3,500mm.This paper will focus on the challenges involved with planning and designing the construction of the 2,470m – 3,500mm diameter tunnel from south of the Canadian Pacific Railway lines on Trafalgar Road to north of the Steeles Avenue and Trafalgar Road intersection. The tunnel is required to facilitate twin 900mm diameter watermains and the shafts will facilitate the construction of the isolation chambers. The tunnel alignment crosses the Canadian Pacific Railway, a tributary of Sixteen Mile Creek, Highway 401, the Toronto Premium Outlet Mall, Steeles Avenue and two box culverts through a confined artesian aquifer with head pressure 1.5m above grade at the intermediate shaft locations near Highway 401.The total length of the tunnel is 2,470m with two intermediate shafts, one north and one south of the Highway 401 to facilitate the construction of interconnection chambers. The longest tunnel drive is 1,062m from the intermediate shaft north of Highway 401. Currently there are no distribution watermains along Trafalgar Road so all residents and businesses in the area rely on the aquifer for their water source, for this reason it was imperative to undertake a design that mitigated impacts to the aquifer.
机译:Zone 4 Feedermain项目涉及从Trafalgar Road和Britannia Road到Trafalgar Road和Side Side No.5附近的Zone 4 Reservoir大约13,000m的干线供水管道的安装。水管设计为采用明挖和非开挖方法进行安装,包括3,100m直径1200mm的给水管,7,070m的900mm直径的双给水管和2,800m的900mm的单个给水管。将通过无沟槽方法安装4,080m的水管,隧道直径范围从1,800mm到3500mm。\ r \ n本文将着重于规划和设计直径2470m – 3500mm的隧道施工所涉及的挑战。特拉法加路(Trafalgar Road)上加拿大太平洋铁路线以南,斯蒂尔斯大道(Steeles Avenue)和特拉法加路(Trafalgar Road)交叉路口以北。需要使用该隧道来支撑直径为900mm的双水管,竖井也将有助于隔离室的建造。隧道路线穿过加拿大太平洋铁路,十六英里溪支流,401高速公路,多伦多高级奥特莱斯购物中心,Steeles大道和两个箱形涵洞,通过一个封闭的自流含水层,在高速公路附近的中间竖井位置上,地头压力高出地面1.5m 401. \ r \ n隧道的总长度为2470m,有两个中间竖井,分别位于401号高速公路的北侧和南侧,以方便互连室的建造。最长的隧道距401号公路以北的中间竖井为1,062m。特拉法加路目前没有配水管,因此该地区所有居民和企业都依靠含水层作为水源,因此必须进行蓄水减轻对含水层影响的设计。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号