首页> 外文会议>Collection systems conference >Taming the Multi-Stakeholder Hydra: A case study in planning, permitting, design and construction of a gravity sewer meeting Federal, State, and Private Stakeholder constraints.
【24h】

Taming the Multi-Stakeholder Hydra: A case study in planning, permitting, design and construction of a gravity sewer meeting Federal, State, and Private Stakeholder constraints.

机译:驯服多方利益相关者九头蛇:在规划,许可,设计和建造满足联邦,州和私人利益相关者约束的重力下水道的案例研究。

获取原文

摘要

This case study will discuss the intricacies in planning, designing, permitting and constructing a large-scale gravity sewer project for Loudoun Water in Loudoun County, VA. Located just west of Washington DC and currently one of the fastest growing areas in the country, Loudoun Water requires this new sewer to meet projected wastewater demands in their Horsepen Run sewershed. The 20,000 linear-foot pipeline of large diameter sewer (72/48/42 inch) crossed only four properties, but affected numerous stakeholders. A large portion of the project crossed the Washington Dulles International Airport, and also required extensive work under and around the new Metro Rail Silver Line. Stakeholders - each with unique and challenging requirements - included the following: 1. Metropolitan Washington Airports Authority (MWAA) 1.1 Federal NEPA applicability/constraints 1.2 Phase I Archaeological Survey 1.3 Specific Federal Aviation Administration blasting requirements 2. Capital Rail Constructors (CRC) (Metrorail Silver Line Phase 2 Design-Build Team) 2.1 Construction work area access 2.2 Coordination of design 2.3 Coordination of schedules 3. Washington Metropolitan Area Transit Authority (WMATA) 3.1 Coordination with ongoing construction project including buried infrastructure 4. Toll Road Investors Partnership Ⅱ (TRIP Ⅱ) - owner of the Dulles Greenway 4.1 Limited Access Highway Break to facilitate maintenance and construction 4.2 Multiple tunnel crossings under roadway and ramps 4.3 Required road closures as a result of blasting operations 5. Virginia Department of Transportation (VDOT) 5.1 Coordination of Horsepen Pond Emergency Spillway and Old Ox Road Widening Project 5.2 Multiple tunnel crossings under roadway and ramps 6. Dulles World Center (DWC a large private development) 6.1 Coordinate future sewer connections and avoidance of tree conservation areas 6.2 Coordination with ongoing construction activities 7. DC Water and Sewer Authority (DC WAS A) 7.1 Coordination for crossings of the Potomac Interceptor (PI), Indian Creek Sewer, and adjacent construction 7.2 Blasting and construction traffic concerns around existing Potomac Interceptor 8. Fairfax County 8.1 Provide capacity for future Fairfax wastewater flows 8.2 Facilitate division of Loudoun Water and Fairfax flow from an existing shared sewer via a flow splitter box and meter vault Timing for the project was driven by anticipated increased demands as well as a desire to design and construct the new sewer prior to construction of WMATA's new Metrorail Silver Line Phase 2, which had to be crossed in four locations. The Owner wanted to avoid conflicts during construction, reduce installation risks in the vicinity of an active light rail line, and avoid having to obtain approval from two federal authorities - MWAA and WMATA. An important nuance of the project is that MWAA is the Owner of the Metrorail Silver Line Project until its construction is complete. The initial concept was to design the project to approximately the 60% design level and install casing pipes to facilitate future installation of the sewer without encroaching into WMATA's easement. Through stakeholder meetings with MWAA it was learned installation of the casing pipes would 1) not preclude the need for future approvals from WMATA, and 2) the necessary easement could not be obtained without a full Phase 1 archaeological survey, 401/404 permit, and encroachment agreements from VDOT, and the Dulles Greenway (TRIP Ⅱ) for the entire pipeline length. Consequently, the design was modified to a 100% design in time to still meet the Owner's initial goal of installing its sewer project before the construction of the Silver Line. The presentation will outline the strategies implemented by the Project team to engage stakeholders and facilitate and expedite their review and approval. In addition to the early coordination with MWAA, there were varying levels of coordination required with each of the major stakeholders for various phases of the project, as summarized above.
机译:本案例研究将讨论在弗吉尼亚州劳登县劳登水务的规划,设计,许可和建设大型重力下水道项目中的复杂性。劳登水务公司位于华盛顿特区西部,目前是该国增长最快的地区之一,它需要这种新的下水道来满足其Horsepen Run下水道的预计废水需求。大直径下水道(72/48/42英寸)的20,000线性英尺管线仅穿越了四个属性,但影响了众多利益相关者。该项目的很大一部分横穿了华盛顿杜勒斯国际机场,还需要在新的地铁银条线下及其周围进行大量的工作。利益相关者(每个人都有独特且具有挑战性的要求)包括以下内容:1.华盛顿大都会机场管理局(MWAA)1.1联邦NEPA适用性/限制条件1.2第一阶段考古调查1.3联邦航空管理局的特定爆炸要求2.首都铁路建设商(CRC)(Metrorail)银线2期设计建造团队)2.1施工工作区通道2.2设计协调2.3时间表协调3.华盛顿都会区运输管理局(WMATA)3.1与正在进行的建设项目(包括地下基础设施)进行协调4.收费公路投资者合作伙伴Ⅱ(TRIP) Ⅱ)-杜勒斯绿道的所有者4.1有限通行的高速公路中断点,以方便维护和建设4.2巷道和坡道下的多个隧道过境4.3爆破作业导致需要的道路封闭5.弗吉尼亚交通部(VDOT)5.1霍彭池塘的协调紧急溢洪道和旧牛路拓宽工程5.2巷道和坡道下的多个隧道过境6.杜勒斯世界中心(DWC是一个大型私人开发项目)6.1协调未来的下水道连接和避开树木保护区6.2与正在进行的建筑活动进行协调7. DC供水和下水道管理局(DC WAS A) 7.1协调Potomac拦截器(PI),Indian Creek下水道和邻近建筑的穿越7.2围绕现有Potomac拦截器的爆破和建筑交通问题8. Fairfax县8.1为将来的Fairfax废水流量提供容量8.2促进Loudoun Water和Fairfax流量的划分通过分流箱和仪表库从现有的共享下水道中抽水。由于预期的需求增加以及在建造WMATA的新Metrorail Silver Line 2期之前设计和建造新下水道的愿望,驱动了该项目的时机。在四个位置交叉。业主希望避免在施工过程中发生冲突,减少活跃的轻轨线附近的安装风险,并避免必须获得两个联邦当局(MWAA和WMATA)的批准。该项目的一个重要细微之处在于,MWAA是Metrorail Silver Line项目的所有者,直到其建设完成。最初的概念是将项目设计到大约60%的设计水平,并安装套管,以方便将来安装下水道,而不会损害WMAT​​A的便利性。通过与MWAA的利益相关者会议得知,套管的安装将不会:1)不排除WMATA将来的批准需求; 2)如果没有完整的第一阶段考古调查,401/404许可,则无法获得必要的便利。 VDOT和Dulles Greenway(TRIPⅡ)达成了整个管道长度的侵占协议。因此,设计已及时修改为100%设计,以仍然满足业主在Silver Line建造之前安装下水道项目的最初目标。该演讲将概述项目团队为吸引利益相关者并促进和加快他们的审核和批准而实施的策略。如上所述,除了与MWAA的早期协调外,在项目的各个阶段与每个主要利益相关者的协调水平也有所不同。

著录项

相似文献

  • 外文文献
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号