CONSTRUCTION OF SOPHISTICATED ENVIRONMENTAL CONTROLED 600MWPULVERIZED COAL FIRED TOWER BOILER FOR URBAN POWER STATION

机译:城市电站600MW环保粉煤细塔锅炉的施工。

获取原文
获取原文并翻译 | 示例

摘要

Replacement project of J-Power's Isogo Thermal Power Station, Yokohama Japan, hasrnbeen carried out. As the first step of the project, construction of 600MW coal fired plant had been carried outrnunder operation of existing 265MW×2 units to be replaced. To adopt limited site area condition, IHI'srntower-type boiler is applied because its compact layout and suitable erection procedure conform to thernreplacement condition. By IHI's Low Nox Combustion technology, the highest steam condition in Japan andrndry-type desulfurization system using activated char, this unit contributes to reduce emission and increasernpower, showing a new solution for replacing urban power station.
机译:日本横滨J-Power的矶子热电厂的更换项目已经开始。作为该项目的第一步,在现有265MW×2台机组的运行下进行了600MW燃煤电厂的建设。为了采用有限的场地条件,使用了IHI的塔式锅炉,因为其紧凑的布局和合适的安装程序符合更换条件。通过IHI的低NOx燃烧技术,日本最高的蒸汽条件和使用活性炭的干式脱硫系统,该装置有助于减少排放并增加功率,为替代城市电站提供了一种新的解决方案。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号