THE NEW STATE-OF-THE-ART OF STAINLESS SLAB PRODUCTION THE NEW SLAB CASTERS FOR AVESTAPOLARIT TORNIO, FINLAND AND ALZ, BELGIUM

机译:最新的不锈钢板生产最新工艺,用于比利时的AVESTAPOLARIT TORNIO和ALZ的新型板坯

获取原文
获取原文并翻译 | 示例

摘要

In November 2000, the Belgian stainless-steel producer ALZ awarded VAI with a contract to upgrade steelmaking plant and increase production. The scope of work included the installation of the world's productive and largest stainless-steel slab caster designed for an annual output of 1.2 million tons. As a major challenge, the existing casting machine had to be replaced within a comprehensive shut-down period ( 21 days only to minimize the financial burden due to the production outage. Therefore special efforts innovative solutions were necessary to accomplish the complete revamp including cold testing within this t schedule. Innovative project management solutions combined with excellent team efforts resulted in a successful start-up OB] October 1, 2002, after a record shutdown period of 20 days only. AvestaPolarit Tornio (APTO) has chosen a different strategy to increase their slab production capacity from 600.000 to 1.65 million tons per year. Instead of revamping the old steelmaking facilities and casting machine APTO awarded an order for building a new high performance stainless steel caster to VOEST ALPINE Industrieanlagenbau (VAI) in 2000. In order to meet APTO's stringent quality demands, the continuous casting machine is equipped with today's most advanced technological caster features. In addition highest productivity is realized with casting speeds up to 1.6 m/min for a casting thickness of 185 mm. Features, details and results of both projects will be discussed together with technologies employed.
机译:2000年11月,比利时不锈钢生产商ALZ授予VAI一份合同,以升级炼钢厂并提高产量。工作范围包括安装世界上生产能力最大的不锈钢板坯连铸机,其设计年产量为120万吨。面临的主要挑战是,必须在全面的停机时间内(仅21天)更换现有的铸造机,以最大程度地减少因生产中断而造成的财务负担。因此,需要做出特殊的努力,创新的解决方案才能完成包括冷试的全面改造在此时间表内,创新的项目管理解决方案与出色的团队合作共同导致了成功的启动[OB] [2002年10月1日,仅在创纪录的20天停工期之后] AvestaPolarit Tornio(APTO)选择了另一种策略来提高他们的板坯生产能力从每年600.000吨至165万吨,而不是改造旧的炼钢设备和铸造机,APTO于2000年向VOEST ALPINE Industrieanlagenbau(VAI)授予了建造新型高性能不锈钢连铸机的订单。 APTO对质量的严格要求,连铸机配备了当今最先进的CAS三重功能。此外,对于185 mm的铸件厚度,高达1.6 m / min的铸件速度可实现最高的生产率。这两个项目的功能,细节和结果将与所采用的技术一起进行讨论。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号