【24h】

Start Up Planning Support Following a Plant Revamp

机译:在工厂改造后启动计划和支持

获取原文
获取原文并翻译 | 示例

摘要

Replacement of the 3 major compressors, multiple tower re-trays and addition of a Demethanizer Pre-Stripper changed plant behavior for plant start up. Relying solely on operator's experience and knowledge of the pre-turnaround plant configuration could affect resolution of the numerous abnormal conditions that arise during the start up sequence of any revamped plant. To alleviate this problem, steady state simulation of each of the start up steps was performed in order to provide process targets. The simulations were also converted into monitoring tools integrated with live plant data acquisition. Distillation tray operating windows, compressor curves and data from other relevant process equipment were obtained from vendors and integrated within the simulation and plant data acquisition interface. Operating conditions were then periodically evaluated and direction given to ensure that equipment was being operated within its design envelope. This paper describes the key design changes affecting the process behavior and how process simulation has been used to provide direction to Operations during the execution of the start up.
机译:更换3台主要压缩机,重新安装多个塔架以及添加脱甲烷塔预剥离器,改变了工厂启动时的工厂运行状况。完全依靠操作员的经验和对周转前工厂配置的了解可能会影响对任何经过改造的工厂的启动过程中出现的众多异常情况的解决。为了缓解此问题,对每个启动步骤进行了稳态仿真,以提供过程目标。模拟也被转换为与现场工厂数据采集集成的监控工具。蒸馏塔盘的操作窗口,压缩机曲线和其他相关工艺设备的数据可从供应商处获得,并集成在模拟和工厂数据采集界面中。然后定期评估运行条件并给出指导,以确保设备在其设计范围内运行。本文介绍了影响流程行为的关键设计更改,以及在启动执行过程中如何使用流程仿真为操作提供指导。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号