Accelerated Replacement of the 4500 South Bridge over I-215 in Salt Lake City, UT Using SPMTs

机译:使用SPMT加速更换犹他州盐湖城I-215上的4500南桥

获取原文
获取原文并翻译 | 示例

摘要

The 4500 South Bridge over I-215 required immediate replacement due to rapid deterioration of the substructure concrete. UDOT implemented the Construction Manager/General Contractor procurement method and Accelerated Bridge Construction techniques to progress construction quickly. The project moved from concept to finished construction in less than 9 months. The bridge was constructed off-site and with a weekend closure of the interstate, the existing bridge was removed and the new bridge was moved into place using self propelled modular transporters.
机译:由于下部结构混凝土的快速变质,I-215上的4500南桥需要立即更换。 UDOT实施了施工经理/总承包商采购方法和加速桥梁施工技术以快速进行施工。在不到9个月的时间里,该项目从概念转变为竣工。这座桥是在场外建造的,州际公路周末关闭,现有的桥被拆除,新的桥使用自行式模块化运输车移到位。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号