首页> 外文会议>2017 International Conference on Electromechanical and Power Systems >Chişinău CHP-1 retrofitting by the proces of installing gas turbines
【24h】

Chişinău CHP-1 retrofitting by the proces of installing gas turbines

机译:基希讷乌第1章,通过安装燃气轮机进行改造

获取原文
获取原文并翻译 | 示例

摘要

Equipped with outdated installations from the nineteen-fifties and nineteen-sixties, Chisinau CHP-1, operates with an electrical efficiency below 20%. However its decommissioning encounters several problems, related to the shortage of power generation in the republic, and to the difficulty of ensuring the thermal load during the summer time. A reasonable solution would be to disassemble the medium pressure boilers and replace them with gas turbine and recovery boilers installations, at the same time keeping the existing steam turbines and electrical equipment. Two gas turbines with 16 ... 38 MW capacity and 35 ... 40% electrical efficiency can be installed in the boiler's space. Recovery boilers would produce steam for the existing turbines increasing the electrical power by 10 ... 14% and the electrical efficiency up to 39 ... 45%. The CHP global efficiency could remain at the current share of up to 88%.
机译:基希讷乌CHP-1配备有19世纪50年代和19世纪60年代过时的装置,其电力效率低于20%。但是,其退役遇到了几个问题,这些问题与共和国的发电不足以及确保夏季热负荷的困难有关。合理的解决方案是拆卸中压锅炉,并用燃气轮机和回收锅炉装置代替它们,同时保留现有的蒸汽轮机和电气设备。可以在锅炉空间中安装两台容量分别为16 ... 38 MW和35 ... 40%的燃气轮机。回收锅炉将为现有的涡轮机产生蒸汽,从而使电功率增加10到14%,电效率提高到39到45%。 CHP的全球效率可能会保持目前高达88%的份额。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号