首页> 外文会议>2016 2nd International Conference on Industrial Engineering, Applications and Manufacturing >“Virtual” power line method to correct the calculation of current ground faults in the parallel overhead transmission lines 110–220 kV
【24h】

“Virtual” power line method to correct the calculation of current ground faults in the parallel overhead transmission lines 110–220 kV

机译:“虚拟”电力线方法可纠正110-220 kV并行架空输电线路中当前接地故障的计算

获取原文
获取原文并翻译 | 示例

摘要

The mutual induction between the phase wires of the different overhead power lines located close to each other causes unbalanced redistribution of currents in the line wires. This leads to emergence of the out-of-balance zero sequence current, which affects negatively on the sensitivity of the zero-sequence current protection. It is impossible to estimate such out-of-balance current by the means of typical calculation programs for short circuit currents. This paper describes the method of “virtual” lines for an extra correction of the values of zero-sequence currents during the 110-220 kV current ground faults occurring in the overhead power lines. There is an example of using this method for three 220 kV parallel overhead lines passing close to each other.
机译:彼此靠近的不同架空电力线的相线之间的互感会导致线路中电流的重新分配不平衡。这导致出现不平衡的零序电流,这对零序电流保护的灵敏度产生负面影响。不可能通过典型的短路电流计算程序来估算这种不平衡电流。本文介绍了一种“虚拟”线路的方法,用于对架空电力线路中发生的110-220 kV电流接地故障期间的零序电流值进行额外校正。对于三个彼此靠近的220 kV平行架空线使用此方法的示例。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号