Design, erection, testing and commissioning of 200Kwp rooftop grid tied solar photovoltaic system at Vasavi College of engineering

机译:瓦萨维工学院200Kwp屋顶并网太阳能光伏系统的设计,安装,测试和调试

获取原文
获取原文并翻译 | 示例

摘要

In this paper a detailed case study has been presented on design, erection, testing and commissioning of 200Kwp solar power plant at Vasavi College of engineering, Ibrahimbagh, Hyderabad. This paper deals with sizing of various equipments, specification of PV modules, Inverters, MCCB, Cables and associated protective equipment. Problems encountered during erection, testing, commissioning and operation and solutions adopted for these problems are discussed. The plant is generating on average 25,000 units per month resulting in a saving of Rs 2.5 lakhs per month in the electricity bill. Problems faced such as cable heating, Reverse power to DG set is dealt. The details of reduction in the efficiency of the plant due to various causes and methods for improvement are also discussed. One protective scheme namely PLC based power balancer protection scheme for DG protection is dealt. The monitoring of the PV plant is also discussed in detail in this paper.
机译:本文对海得拉巴易卜拉欣巴格的瓦萨维工程学院200Kwp太阳能发电厂的设计,安装,测试和调试进行了详细的案例研究。本文涉及各种设备的尺寸,PV模块,逆变器,MCCB,电缆和相关保护设备的规格。讨论了在安装,测试,调试和运行过程中遇到的问题以及针对这些问题采取的解决方案。该工厂每月平均发电25,000台,每月可节省25万卢比的电费。解决了诸如电缆发热,DG装置的反向电源等问题。还讨论了由于各种原因而导致工厂效率降低的细节以及改进方法。提出了一种保护方案,即基于DG的基于PLC的功率均衡器保护方案。本文还将详细讨论光伏电站的监控。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号