Application of Proportion Method to the Calculation of Overhead Associated with Owner-caused Delay

机译:比例法在所有者延迟引起的间接费用计算中的应用

获取原文
获取原文并翻译 | 示例

摘要

During the completion of public construction projects, deadlines are often delayed due to unfavorable weather, design changes, delayed site delivery by the owner, or other unpredictable circumstances. Contractors can declare delays that are not attributable to themselves as owner-caused delays, for which they can demand compensation for the additional costs they incur. However, current construction contracts often lack specifications regarding compensable items and reasonable overhead associated with owner-caused delay. Vague clauses in this aspect are often the cause of construction disputes [1]. This study focused on current issues related to overhead compensation associated with owner-caused delay. We calculated the amount of compensation in an empirical case study using the proportion method and the expenditure method, respectively, to identify the superior model. The expenditure method requires transaction records, and although it is currently the most common approach to resolving disputes, verifying transaction records is difficult. In comparison, the proportion method is simpler and follows accepted practices in the construction industry. In our case study, the expenditure method was more time-consuming compared to the proportion method, and the resulting compensation amounts differed only minutely (0.035 %). Therefore, the proportion method is considered a preferable approach. The structured calculation model proposed in this study follows current practices and can be used as a reference for future contracts.
机译:在公共建设项目完成期间,由于天气,设计变更,业主的现场交付延迟或其他不可预测的情况,往往会延迟截止日期。承包商可以将不能归因于自己的延误声明为业主造成的延误,为此,承包商可以要求赔偿所产生的额外费用。但是,当前的施工合同通常缺乏有关可补偿项目的规范以及与业主造成的延误有关的合理开销。在这方面模糊的条款通常是造成建筑纠纷的原因[1]。这项研究的重点是与所有者造成的延迟相关的间接费用补偿相关的当前问题。我们分别使用比例法和支出法计算了经验案例研究中的补偿金额,以识别上级模型。支出方法需要交易记录,尽管它是当前解决争端的最常用方法,但很难验证交易记录。相比之下,按比例分配的方法更简单,并且遵循建筑行业公认的惯例。在我们的案例研究中,与比例法相比,支出法更加耗时,并且最终的补偿金额仅相差微小(0.035%)。因此,比例法被认为是优选的方法。本研究中提出的结构化计算模型遵循当前做法,可以用作将来合同的参考。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号