SAFETY EVALUATION OF DELAMINATED CONTAINMENT DOME REENGINEERING

机译:脱层防护罩再工程的安全性评估

获取原文
获取原文并翻译 | 示例

摘要

Delamination of the inner (primary) containment dome of the Kaiga Atomic power project, Unit-1 occurred duringrnconstruction. The containment dome delamination was investigated in detail. Subsequent to the investigation of therndelamination phenomenon, re-engineering (re-design and re-construction) of the dome was initiated. Methodology for safetyrnevaluation of re-design and re-construction of the IC dome was suitably devised based on the outcome of the investigationrnwork and the same was implemented. Emphasis was laid, during safety evaluation, on the safety of existing ring beam,rndevelopment of review basis for re-engineered dome, design review and quality assurance in design, quality assurance ofrnmaterials used, examination of constructibility with the new design, and quality assurance of construction of the reengineeredrndome. The inner containment structure was accepted after the successful pre-commissioning proof (structuralrnintegrity) and leakage rate tests.
机译:Kaiga原子能项目1单元的内部(主要)安全壳分层在施工过程中发生。详细研究了安全壳穹顶分层。在调查了热分层现象之后,对圆顶进行了重新设计(重新设计和重建)。根据调查结果适当设计了重新设计和重建IC球罩的安全性评估方法,并实施了该方法。在安全评估期间,重点在于现有环形梁的安全性,重新设计穹顶的评审基础的开发,设计中的设计评审和质量保证,所用材料的质量保证,新设计的可施工性检查以及质量保证重新设计的圆顶建筑。内部安全壳结构在成功的预调试证明(结构完整性)和泄漏率测试之后被接受。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号