Method of effecting fast turbine valving for improvement of power system stability

机译:实现快速涡轮阀控制以提高电力系统稳定性的方法

摘要

As an improved way of effecting fast valving of turbines of power system steam-electric generating units for the purpose of improving the stability of power transmission over transmission circuits to which their generators make connection .Iadd., .Iaddend.when stability is threatened by line faults and certain other stability endangering events, and in which intercept valves are rapidly closed on a momentary basis, the procedure of intercept valve closure is supplemented by simultaneously initiating turbine and steam supply source control programs, which (a) .[. being.]. .Iadd.bring .Iaddend.into effect a sustained reduction in turbine driving power via employment of measures which may include full closing of some or all control valves and/or employment of preprogrammed control valve repositioning, with provision to automatically divert high pressure steam to the condenser or to atmosphere as a way to prevent discharge of steam through high pressure safety valves. (b) bring into effect a rapidly executed process of reduction of rate of generation of steam within steam supply sources, and (c) initiate a control program that effects a predetermined degree of partial reopening of intercept valves early in the course of the generator rotor's first backward swing, following which intercept valves are further opened and control valve positions optionally revised in preprogrammed ways with the overall effect that in the period following the first forward swing the magnitude of turbine driving power is caused to hold below the value that applied prior to the event that initiated fast valving and to at most only briefly exceed a final sustained value that can be preset.
机译:作为改善电力系统蒸汽发电机组涡轮机快速阀的一种改进方法,目的是提高当发电机的发电机连接到的输电线路通过输电线路进行输电时,输电线路的稳定性。故障和某些其他危及稳定性的事件,并在短时间内迅速关闭截流阀时,通过同时启动涡轮机和蒸汽供应源控制程序来补充截流阀的关闭过程,该程序(a)。存在。]。通过采取措施,包括完全关闭部分或全部控制阀和/或使用预先编程的控制阀重新定位,并自动将高压蒸汽转移到其他位置,以实现涡轮机驱动功率的持续降低。冷凝器或大气,以防止蒸汽通过高压安全阀排放。 (b)迅速执行降低蒸汽供应源中蒸汽产生速率的过程,并且(c)启动控制程序,该程序在发电机转子的运行过程中尽早实现预定程度的节流阀部分重新开启。第一向后回转,随后进一步打开截流阀,并以预编程的方式可选地调整控制阀位置,其总体效果是,在第一向后回转之后的一段时间内,使涡轮机驱动功率的大小保持在低于之前的值启动快速阀门并且最多仅短暂超过可以预设的最终持续值的事件。

著录项

  • 公开/公告号USRE29485E

    专利类型

  • 公开/公告日1977-11-29

    原文格式PDF

  • 申请/专利权人

    申请/专利号US19750630724

  • 发明设计人 ROBERT H. PARK;

    申请日1975-11-10

  • 分类号F01K13/02;

  • 国家 US

  • 入库时间 2022-08-22 21:24:14

相似文献

  • 专利
  • 外文文献
  • 中文文献
获取专利

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号