首页> 外国专利> METHOD OF ENHANCING POWER CAPACITY OF PUMPED-STORAGE POWER PLANT

METHOD OF ENHANCING POWER CAPACITY OF PUMPED-STORAGE POWER PLANT

机译:提升水电厂容量的方法

摘要

The invention relates to hydraulic structures and can be used in the construction and reconstruction of a pumped storage plant (PSPP). The purpose of the invention is to reduce the amount of construction work and material consumption. The complex of the power plant contains the upper bass. Sein 1, pressure shaft 2, power plant building 3, lower sealed pool 4, ventilation drift 5, airtight hatch with a check valve 6. The increase in the energy capacity is performed as follows. First, the lower basin 4 is filled with water, it is sealed and the water is pumped from the lower basin 4 to the upper basin 1. At the same time, as the volume and water level in pool 4 decreases, a vacuum will be created in it. When the power plant is turned on in the generator mode, the total pressure on the hydraulic unit will be equal to the sum of the static pressure and the increment obtained as a result of creating a vacuum on the surface of the water in the lower pool of 4. 1 Il. I (L
机译:本发明涉及水力结构,并且可用于抽水蓄能电站(PSPP)的建设和重建。本发明的目的是减少建筑工作量和材料消耗。发电厂的建筑群包含高低音。围网1,压力井2,发电厂3,下部密封水池4,通风装置5,带有止回阀6的气密舱口。能量增加的过程如下。首先,将下水盆4装满水,将其密封,然后将水从下水盆4泵送到上水盆1。同时,随着池4中的水量和水位降低,真空度将增加。在其中创建。在发电机模式下打开发电厂时,液压单元上的总压力将等于静压力与在下部泳池水面产生真空所获得的增量之和。的4. 1 Il。我(L

著录项

相似文献

  • 专利
  • 外文文献
  • 中文文献
获取专利

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号