首页>
外国专利>
Tunnel lining concrete placing facilities method and the arch center
Tunnel lining concrete placing facilities method and the arch center
展开▼
机译:隧道衬砌混凝土浇筑设施的方法和拱中心
展开▼
页面导航
摘要
著录项
相似文献
摘要
PURPOSE:To make it possible to place a better concrete lining with no steps of joint in a construction joint on a side wall by absorbing the side pressure of concrete in case of concrete placement by a portal which is antecedently displaced. CONSTITUTION:A portal 5 and a height of a ceiling end part of a centre 6 are set, and displacement much more than the amount of displacement added to a side wall centre 1 is provided to the portal 5 in advance in case of concrete placement. The provision of the antecedent displacement is made by an antecedent displacement provided substance 10. The side pressure of the concrete 8 in case of concrete placement is absorbed by the portal 5 which is antecedently displaced.
展开▼