CONSTRUCTING METHOD OF TEMPORARY TRACK FOR TUNNELING WORK, AND SLEEPERS FOR TEMPORARY TRACK USED THEREFOR
CONSTRUCTING METHOD OF TEMPORARY TRACK FOR TUNNELING WORK, AND SLEEPERS FOR TEMPORARY TRACK USED THEREFOR
展开▼
机译:隧道工作临时轨迹的构造方法以及使用此临时轨迹的衬套
展开▼
页面导航
摘要
著录项
相似文献
摘要
PROBLEM TO BE SOLVED: To enlarge an inner space height so that a worker can walk through easily and that a drain of a large diameter can be brought in immediately after primary lining and thereby to make working efficient. ;SOLUTION: In parallel with excavation of a tunnel by a shield machine S, sleepers 3 to be used on the occasion of primary lining are provided inside primary lining segments installed completely, at height positions enabling parallel running of following trucks 6 brought to the rear side of the shield machine S and of a carrying vehicle running in the tunnel, while rails 1 whereon the following trucks 6 and the carrying vehicle run are laid therein. On the other hand, the sleepers 3 used on the occasion of the primary lining are removed sequentially from places where the following trucks 6 advancing with the shield machine S have ended passing, on the rear side of the laid rails, and sleepers 5 to be used on the occasion of secondary lining are provided at height positions lower relatively than the sleepers 3, while the rails 1 whereon the carrying vehicle runs are relaid.;COPYRIGHT: (C)1999,JPO
展开▼