首页> 外国专利> METHOD FOR CONSTRUCTING SUBWAY TUNNEL WITH TWO-STAGE SHIELD MACHINE

METHOD FOR CONSTRUCTING SUBWAY TUNNEL WITH TWO-STAGE SHIELD MACHINE

机译:两级屏蔽机构建地铁隧道的方法

摘要

PROBLEM TO BE SOLVED: To enhance utilization efficiency of a shield machine by extending the section of execution by at two-stage shield machine, make the execution more efficient, and reduce construction costs.;SOLUTION: A first shaft 35 is constructed at an end of one side of a station part 36; the two-stage shield machine M, housing child shield machines 2A and 2B, is assembled inside the first shaft 35; the shield machine M is started from the first shaft 35 so as to excavate the station part 36; and when the shield machine M reaches the second shaft 39 constructed at an end on the other side of the station part 36, the shield machines 2A and 2B are started to excavate a line part 37 continuing into the station part 36. A parent shield machine 1 is dismantled to be removed from the second shaft 39 and constructed at an end on one side of a next station part 38 in order to be assembled inside a third shaft 40; and when reaching the third shaft 40 of the station part 38, the shield machines 2A and 2B are made to coalesce into the shield machine 1, so that the station part 38 can be excavated by the shield machine M, in which the shield machines 2A and 2B coalesce into the shield machine 1.;COPYRIGHT: (C)2002,JPO
机译:解决的问题:通过扩展两级屏蔽机的执行部分来提高屏蔽机的利用效率,使执行效率更高,并降低建造成本。;解决方案:在末端构造了第一轴35站部分36的一侧;在第一轴35的内部组装有容纳儿童屏蔽器2A,2B的两级屏蔽器M。屏蔽机M从第一轴35启动,以挖掘站部分36。当屏蔽机M到达构造在工位部分36另一侧的端部的第二轴39时,屏蔽机2A和2B开始挖掘继续进入工位部分36的管线部分37。拆卸图1所示的组件以将其从第二轴39上拆下,并构造在下一个工位部分38的一侧的一端,以便组装在第三轴40内。当到达屏蔽罩2时,屏蔽机2A和2B在到达站部38的第三轴40时合并到屏蔽机1中,从而可以通过屏蔽机M挖掘屏蔽罩2A。和2B并入屏蔽机1 .;版权:(C)2002,JPO

著录项

相似文献

  • 专利
  • 外文文献
  • 中文文献
获取专利

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号