首页> 外国专利> Method for making reinforced concrete tunnel from terrain surface, engineering structure for making such reinforced concrete tunnel as well as the reinforced concrete tunnel per se

Method for making reinforced concrete tunnel from terrain surface, engineering structure for making such reinforced concrete tunnel as well as the reinforced concrete tunnel per se

机译:从地形表面制造钢筋混凝土隧道的方法,制造该钢筋混凝土隧道的工程结构以及钢筋混凝土隧道本身

摘要

The proposed method for making reinforced concrete tunnel from terrain surface, the side walls (1) of which are formed successively as individual longitudinal sections (2, 3) of the tunnel, is based on that the individual sections (2, 3) are alternately terminated from below in the ground as longer and shorter ones. First, both sidewalls (1) are formed that are then coupled from above with a ceiling structure (4). Subsequently soil (14) is removed at least on one side of the ceiling structure (4) downward forming thus a main adit underground haulage passage (6) all over the future tunnel length for handling material and hardware necessary for tunnel construction, whereupon rock or soil (14) is removed from a space extending between entrances of the future tunnel. Rock or soil (14) is removed up to the level of the future bottom surface of the tunnel bottom (5) and for the length of at least two adjacent (2, 3). Disclosed is also an engineering structure comprising two reinforced concrete side walls (1) coupled with a reinforced ceiling structure (4) with a main adit underground haulage passage (6) extending underneath and all over said ceiling structure (4) length and being recessed in rock or soil (14). Said sidewalls (1) terminate in sections (2, 3) in the soil alternately as longer and shorter ones. A stope (9) being interconnected with said main adit underground haulage passage (6) and extending up to the tunnel bottom (5) structure is arranged beneath said passage (6). Another object of the present invention is a reinforced concrete tunnel made from terrain surface in the above-described manner.
机译:从地形表面制造钢筋混凝土隧道的建议方法是,其侧壁(1)依次形成为隧道的各个纵向部分(2、3),其基于各个部分(2、3)交替排列从地下终止在地下,成为更长或更短的。首先,形成两个侧壁(1),然后从上方将其与天花板结构(4)耦合。随后,至少在顶棚结构(4)的一侧向下除去土壤(14),从而在整个未来的隧道长度上形成一条主要的地下运输通道(6),以处理隧道施工所需的材料和硬件,从而使岩石或从在未来隧道的入口之间延伸的空间中除去土壤(14)。去除岩石或土壤(14)直至到达隧道底部(5)的下一个底部表面的高度,并去除至少两个相邻的(2,3)的长度。还公开了一种工程结构,该工程结构包括两个钢筋混凝土侧壁(1)和一个钢筋天花板结构(4),该天花板结构(4)具有在底部天花板结构(4)的整个长度范围内延伸并凹入其中的主平巷地下运输通道(6)。岩石或土壤(14)。所述侧壁(1)在土壤的部分(2、3)中交替地变长和变短。在所述通道(6)的下方设置有与所述主要通道地下运输通道(6)互连并延伸至隧道底部(5)结构的采场(9)。本发明的另一个目的是一种以上述方式由地形表面制成的钢筋混凝土隧道。

著录项

  • 公开/公告号CZ20021827A3

    专利类型

  • 公开/公告日2003-10-15

    原文格式PDF

  • 申请/专利权人 METROSTAV A. S.;

    申请/专利号CZ20020001827

  • 发明设计人 BUCEK MILOS PROF. ING. DRSC.;

    申请日2002-05-27

  • 分类号E02D29/045;E02D29/00;E02D29/055;

  • 国家 CZ

  • 入库时间 2022-08-22 00:03:31