Piles and Footing Construction Method Using Caisson as Waterproofing Temporary Retaining Well and Concrete Form in Bridge Construction
Piles and Footing Construction Method Using Caisson as Waterproofing Temporary Retaining Well and Concrete Form in Bridge Construction
展开▼
机译:沉井防水临时固井及桥梁施工中桩基施工方法
展开▼
页面导航
摘要
著录项
相似文献
摘要
PURPOSE: Provided is a process for constructing pile base by applying caisson structure as seepage barrier or temporary construction wall body and to utilize the structure as a cast for concrete introduction in digging in ground at a position for a sub-foundation of bridge. CONSTITUTION: The process comprises steps of placing a caisson(1) on a position of a ground to install a bridge pier; mounting the caisson at desired location by excavating the ground and sinking the caisson; re-filling earth and sand into the excavated hollow and constructing the pile; and using the caisson as a cast for introducing concrete into a base plate. A shoe(2) is mounted on front end of the caisson(1) and used to easily insert the caisson into the ground. The re-filling process is for eliminating problems caused by boiling or heaving states in sand/viscous earth such as clay grounds.
展开▼