首页> 外国专利> Apparatus for adjusting position and maintaining function according to lifting the upper structure of bridge, and construction method for lifting up the upper structure

Apparatus for adjusting position and maintaining function according to lifting the upper structure of bridge, and construction method for lifting up the upper structure

机译:一种根据桥梁上部结构的升降调节位置和保持功能的装置及上部结构的升降方法

摘要

The present invention mounted on a conventional T Chair tooth shape by adjusting its position when all kinds of the bridge superstructure of the girder is used for curved parts of pieces gradient gateun slab and normal bridge beyond the location binary appointed on the pier and alternating or as by mounting the binary appointed position after the maintenance of the device gyojwa relates to a construction method using the position adjusting function and a holding apparatus according to an impression of the bridge superstructure to prevent the said girder nakgyo to implement such operation,; Fixing the bracket to the support perpendicular to the alternating long side of the girder lower if the shift install the position adjustment and the function holding unit to the anchor bolt and provided on the bracket wherein the vertical support to the vertical direction yuapjaek between the girder and the vertical support bracket and the securely fixed to the vertical reaction force against and install the sliding buffer pad to the girder side in the opposite direction to that installation over the horizontal support in the long side of the shift to move the bridge superstructure to the horizontal support subject on the entire surface of one side of the vertical support bracket and in the horizontal direction yuapjaek reaction force against the said installation in a horizontal direction yuapjaek on the stand is installed on the horizontal yuapjaek reaction for between one side of the vertical supporting bracket and the horizontal direction yuapjaek while installed horizontally yuapjaek reaction force against the lower portion of the horizontal support the sliding between the lower surface of the upper part and the horizontal support By installing the inner plate installed a sliding cushion pad therebetween, and then using the bridge superstructure moves the steel bar horizontally yuapjaek reaction force against the installed adjacent to the anchorage provided on the outermost surface of the shift of the direction in which secures the fixing,; The position adjustment and the function holding unit connected to each other when installing on a pier while the vertical supporting installation secure the bracket to anchor bolts on both sides of the pier long side of the girder the lower the connection rod and the vertical support bracket is installed on the other side of the fixed and girders and the while mounted on the vertical support bracket in a vertical direction yuapjaek and install over the horizontal support in the long sides of the pier on the entire surface of one side of the vertical supporting brackets between the vertical support bracket in the opposite direction to move the bridge superstructure of that installation the sliding buffer pad to the girder side and a fixed installation a vertical reaction force against the horizontal support target and installing horizontally yuapjaek reaction force against the lower portion of the horizontal support one side of the horizontal direction yuapjaek reaction force against the said vertical support bracket horizontally on the stand is installed on the horizontal direction against the reaction force between yuapjaek Direction while yuapjaek install and install the sliding guide plate between the lower surface of the upper part and the horizontal support in the horizontal direction yuapjaek installed a sliding cushion pad therebetween, and then are installed on the outermost surface of the bridge direction in which the upper structure is moved pier anchorage the adjacent horizontal yuapjaek reaction force against the installed with a fixed fixing install the positioning and the function holding apparatus using a steel rod and then by operating the vertical direction yuapjaek upwardly bridge one the upper structure of the girder a distance increase from gyojwa device following and it is to release the oil pressure at a planned distance moved by the progress to be moved a predetermined distance raise the girders by using the horizontal direction, and then the yuapjaek yuapjaek seating of the girder bridge superstructure on gyojwa device.
机译:当将各种形式的大梁桥上部结构用于梯度闸墩板和普通桥的弯曲部分时,通过调节其位置,将本发明安装在传统的T椅齿形上,超出桥墩指定的位置并交替或作为通过在装置的维护之后安装二进制指定位置,gyojwa涉及一种使用位置调节功能的构造方法和一种根据桥梁上部结构的印象的保持装置,以防止所述大梁进行这种操作;如果移位将位置调节和功能固定单元安装到地脚螺栓上,则将支架固定到垂直于大梁交替长边的支架下部,并设置在支架上,其中,在大梁和垂直支撑支架和牢固地固定在垂直反作用力上,将滑动缓冲垫以与在移位的长边上水平支撑上方相反的方向安装和安装到梁侧,以将桥梁上部结构移至水平方向支撑对象在垂直支撑支架的一侧的整个表面上并在水平方向上产生反作用力yuapjaek反作用于所述装置的水平方向上的yuapjaek在支架上安装在水平yuapjaek反作用力上,用于垂直支撑支架的一侧之间和水平方向yuapjaek而水平安装yuap猛烈的反作用力抵抗水平支撑的下部,在上部的下表面和水平支撑之间滑动通过安装内板,在两者之间安装了一个滑动缓冲垫,然后使用桥上部结构水平移动钢筋yuapjaek反应对固定在固定方向的最外表面上的锚固附近的安装件施加力;当垂直支撑装置将支架固定到大梁的墩长侧两侧的地脚螺栓上时,位置调节和功能保持单元相互连接,而下部连杆和垂直支撑支架则固定在下方。安装在固定梁和大梁的另一侧,而在垂直方向上安装在垂直支撑架上yuapjaek并在水平支撑上安装在墩台长边的垂直支撑架的一侧的整个表面之间垂直支撑支架向相反方向移动,该桥的上部结构将滑动缓冲垫安装到大梁侧,固定安装将垂直反作用力作用在水平支撑目标上,水平安装yuapjaek反作用力作用在水平结构的下部支撑水平方向的一侧yuapjaek反作用力对抗t他说,水平支撑在架子上的垂直支撑架是在水平方向上抵抗yuapjaek方向之间的反作用力而安装的,在yuapjaek安装过程中,将滑动导向板安装在上部的下表面和水平支撑之间的水平方向上yuapjaek安装了滑动垫之间,然后安装在沿上部结构移动的桥方向的最外表面上,用固定的固定件对相邻的水平yuapjaek反作用力进行锚固,以固定方式安装使用钢的定位和功能保持装置杆,然后通过在垂直方向上操作yuapjaek向上桥接大梁的上部结构,从而使距距gyojwa设备的距离增加,并且该油压将释放由计划移动的计划距离的油压,以移动预定距离来升高大梁通过使用水平方向,然后yyojajaek yuapjaek在桥架上的梁桥上部结构的座位。

著录项

  • 公开/公告号KR100522294B1

    专利类型

  • 公开/公告日2005-10-19

    原文格式PDF

  • 申请/专利权人

    申请/专利号KR20030081877

  • 发明设计人 노윤근;

    申请日2003-11-18

  • 分类号E01D21/00;

  • 国家 KR

  • 入库时间 2022-08-21 22:03:20