首页> 外国专利> STRUCTURE MAIN PIPE FORM OF CONSTRUCTION WORK AND THE SPACE-TIME TO ESTABLISH TUNNEL FORMATION TUNNEL STRUCTRUE

STRUCTURE MAIN PIPE FORM OF CONSTRUCTION WORK AND THE SPACE-TIME TO ESTABLISH TUNNEL FORMATION TUNNEL STRUCTRUE

机译:施工工作的结构主要管道形式和建立隧道构造隧道的时空

摘要

The main tube construction method and structure for installing a tunnel construction tunnel structures for forming, ; quickly the plurality of main pipes in the ground for forming a tunnel in a straight line or curve, and by using this simple and outside the tunnel by providing a specific method and construction structure that can be constructed without the risk of safety accident By building a tunnel structure to withstand the stresses from, ; As a result, water features and fewer people without regard to properly designed tunnel straight or curved, etc. Are the conditions in underground equipment and Using the simple and durable materials than in the form of a tunnel, and is designed to be placed as its object the construction completely in a short time. ; one embodiment of the present invention for achieving the object as described above Looking at the example, ; Landmark or seen fit various types of conditions such as to install a tunnel structures for forming a circular tunnel with a steel pipe or timber tube (300) cut to length or square in the Mediterranean As long installation in connection to the main pipe underground (100), ; Leading tube (10), but the installation insert the main tube 20 to the inner surface, ; Leading tube (10) and its reaction force against the inner surface of each of a predetermined number corresponding to each other at a predetermined interval on the inner surface of the inserted main tube 20, 31 and 32, respectively, and the installation for the reaction force between the two sides 31 and 32 installed oil, pneumatic leading to ground 100 using yuapjaek 40 in a state where the forward loading of the cylinder (30) tube (10) and the main tube 20, and the step of press-fitting, ; The leading pipe 10 and when the press of the main pipe leading to pipe 20, 10 is prevented, and then sequentially input connected to the earth dug up prevention plate 12 prevents the surrounding soil through the earth plate slot 11 formed in the plate and earth (12 ) and the step of preventing the earth by the grouting to grout grouting material over to form a part (13), ; The Underground (100) leading inserted into the tube (10) in the main hall floor space reserved ( to its original shape after welding, but the next tube is equally divided into several carrying a main pipe (20 ') in the 200), first removing the reaction force against the back 32 and the oil, the pneumatic cylinder 30 is installed on the existing main pipe (20) The next quarters while the main pipe (20 ') inserted an existing main pipe (20) and coupling welded to the front end, ; The main tube (20 welded to the tubular' back in) for reaction (32) the installation, this lead pipe (10) feeding the reaction force between the front vs. (31) formed on the inner surface, installing a pneumatic cylinder (30), and then to work with this manual and auto-indentation in the ground (100) reaction leading to the main pipe (20) (20 '), tubes (10) leading to propel a predetermined length in the forward pipe 10 and the propulsive phase, ; Leading tube as described above (10) inside and the main tube 20, oil provided between the reaction force versus 31 and 32 provided in the inner surface, the pneumatic cylinder 30, the main tube leading tube was secured after pushing (10) by a predetermined length by using the installation space ( 200) is equally divided into several main tube next through 20 repeat the operation for connecting to the main pipe for installing the tunnel structure for a tunnel formation (20) comprises the step of completing the tunnel-like construction as in the ground (100) its features are the yirueojim to.
机译:安装隧道施工的主管施工方法和结构通过提供一种可以在没有安全事故风险的情况下进行建造的特定方法和施工结构,在地面上迅速形成地面上的多个主管,以形成一条直线或曲线,并通过在隧道的外部使用这种简单的方法承受压力的隧道结构;结果,水的特点和人员的减少而无需考虑正确设计的直管或弯管等。地下设备的条件和使用简单耐用的材料要比以隧道的形式使用,并且被设计为以其形式放置在短时间内完全反对施工。 ;用于实现上述目的的本发明的一个实施例。具有里程碑意义或可见度的条件适合各种类型的条件,例如安装隧道结构以形成圆形隧道,并在地中海中将钢管或木管(300)切成一定长度或正方形,与地下主管连接的安装时间较长(100) ),;导管(10),但安装时将主管20插入内表面;在插入的主管20、31和32的内表面上以预定间隔分别相对应的,预定数量的彼此对应的预定数量的内表面上的导管(10)及其反作用力,以及用于反应的装置在两侧安装的机油31和32之间施加力,在气缸(30)管(10)和主管20向前加载的状态下使用yuapjaek 40气动通向地面100,并进行压配合步骤, ;防止引导管10以及在主管被压向管20时被压入,然后依次输入连接到防挖板12上,防止周围的土壤通过形成在板中的接地板槽11而接地(12)和通过灌浆防止土壤灌浆以形成灌浆材料以形成部分(13)的步骤;地下管线(100)插入保留在大厅内的管道(10)中(在焊接后恢复为原始形状,但下一根管道在200中被分成几根承载主管(20')),首先去除对靠背32和油的反作用力,将气缸30安装在现有主管(20)上。接下来的四分之一,同时主管(20')插入现有主管(20)并焊接到联轴器上。前端;主管(20焊接在管子的后部)用于反作用(32)的安装,该引线管(10)在前表面与内表面上形成的(31)之间提供反作用力,并安装了一个气压缸( 30),然后使用此手册并在地面(100)上进行自动压痕,从而导致通向主管(20)(20')的管道,通向前管10的预定长度的管(10)和推进阶段;如上所述的引导管(10)和主管20的内部,设置在反作用力相对于内表面的31和32之间的油,气压缸30,推动管(10)之后的主管被固定。通过使用安装空间(200)将预定长度分成相等的几根主管,然后通过20次重复用于连接主管的操作,以安装用于形成隧道的隧道结构(20),包括完成隧道状的步骤如地面(100)那样的建筑,其特点就是以意为生。

著录项

  • 公开/公告号KR20060037213A

    专利类型

  • 公开/公告日2006-05-03

    原文格式PDF

  • 申请/专利权人 NTS ENGINEERING&CONSTRUCTION CO. LTD.;

    申请/专利号KR20040091846

  • 发明设计人 KIM JEONG YOON;

    申请日2004-11-11

  • 分类号E21D9/06;

  • 国家 KR

  • 入库时间 2022-08-21 21:25:58