首页> 外国专利> Continuous multi-span bridge using bridge girder units and construction method thereof

Continuous multi-span bridge using bridge girder units and construction method thereof

机译:使用桥梁单元的连续多跨桥及其施工方法

摘要

The present invention takes a large amount of material unnecessarily hameuroseo build a bridge by making a bridge girder on the basis of the maximum bending moment size calculated excessive when making girder for bridge construction is also to be applied to construction cost is excessive due to the labor costs to reduce as much surplus moment size due to the maximum bending moment magnitude and the difference between simple beam was applied to the previous maximum bending moment magnitude occurred when sequencing a bridge to be built in the future when making unit bridge girders to eliminate the wasteful factors the span can be built using the unit as a bridge girder structure with sequencing production relates to the construction method of bridge. ; Installing the steel over a predetermined length on the upper flange of the side end portions, but the bottom flange of installing a length of steel to be a predetermined length extending from the respective side end portions and central portion, and installing a steel frame over a predetermined length, abdomen abdomen at regular intervals between the abdominal sujikjae installing a sujikjae is a temporary fixing block to the inside of the side end portions and provided on both sides of the abdomen sujikjae a pair of temporary fixing block with a predetermined spacing above the lower flange of the central part forms a drilling on the lower flange the bottom flange after installing a one on either side of the abdomen sujikjae installing permanent fixing block to right sides of the upper flange of the lower abdomen sujikjae top of that position, and install a steel material of a predetermined number in the lower flange, and pouring concrete curing after settling in fixed tension to the tensile force acts on the installed steel bars and are installed in a temporary settlement block and bridge girder production unit, ; While assembling steel and connection of the unit bridge girder predetermined length extending presented adjacent to the installed steel frame installed on one end of the unit of the bridge girder after the unit of bridge girders which a mounted on the pier, or alternately forming the connection, the unit of the bridge girders after the was off certain inward distance from the one end to enter into a temporary fixing block and the temporary fixing block installed to an end of the other side is installed on the lower flange to the steel bar fixed, permanent fixing block and adjacent to installed the other is installed on one end of the upper flange introducing a tensile force after the permanent connected to each other by the fixing block of the end bars, and pouring concrete for connection curing and relates to a construction method of a multi-span bridge sequencing installed by removing the temporary fixing steel rods connected to the block. ; When you build a unit the span sequencing bridge using a bridge girder of the present invention, through the installation step-by-step how to construction the separation of the frontal garment size and cross-sectional configurations, such as to reduce the weight for later hypotheses upon the completion, generating girders and reducing unnecessary moments in size and because of this, and to avoid excessive use of hyeonggo and material of the girder to achieve an economical bridge construction, respectively installing the steel frame on the top and bottom flanges of the end and mid-effective synergy of the composite member and to reap a, since the arrangement of the rod which is installed a linear shape can be eliminated the tensile force decrease due to friction of the interference and the sheath of the reinforcement than that of the conventional parabolic arrangement has a construction such as a simple and easy to be effective .
机译:本发明不必要地花费大量的材料,通过基于计算出的最大弯矩尺寸来制造桥梁来制造桥梁,从而不必要地使桥梁架起来。由于最大弯矩大小而要减少尽可能多的剩余弯矩大小的成本,并且在将来对将要建造的桥梁进行排序以消除无用的梁时,将简单梁之间的差异应用于以前的最大弯矩大小会发生使用该单元作为桥梁结构可以建立跨度的因素,排序生产与桥梁的建造方法有关。 ;在侧端部的上凸缘上以预定长度安装钢,但是在从各侧端部和中央部延伸出预定长度的长度上安装钢的长度的底部凸缘,并在钢制框架的上方安装钢框架。预定长度,在腹部sujikjae之间以固定间隔的腹部腹部是在侧端部内侧的临时固定块,并且在腹部sujikjae的两侧上在下部下方以预定间隔设置有一对临时固定块。在腹部sujikjae的任一侧都安装一个法兰后,在下部法兰的中央法兰上钻一个孔,在该位置的下部腹部sujikjae上法兰的右侧安装永久性固定块,并在底部法兰上钻一个孔。下部法兰中具有预定数量的钢材,并以固定的张力将混凝土浇筑固化反作用力作用在已安装的钢筋上,并安装在临时沉降块和桥梁生产单元中;在组装钢和连接单元梁的预定长度延伸时,与安装在桥墩单元上的安装钢架相邻,该已安装的钢框架安装在桥墩上,该单元安装在桥墩上,或者交替形成连接,桥梁的单元从一端离开一定的向内距离后进入临时固定块,并将临时固定块安装到另一侧的一端,并安装在下部法兰上,以永久固定固定块与相邻安装的另一块安装在上凸缘的一端,在通过端杆的固定块彼此永久连接后引入拉力,并浇筑混凝土进行连接养护,涉及一种施工方法通过拆除连接到模块的临时固定钢棒来安装多跨桥序列。 ;当您使用本发明的桥梁建造跨度排序桥时,通过逐步安装,如何构造正面服装尺寸和横截面构造的分离,以减轻以后的重量假设完成后,生成大梁并减少不必要的弯矩,因此,为避免过度使用hyeonggo和大梁的材料来实现经济的桥梁结构,请分别将钢制框架安装在桥的顶部和底部法兰上由于可以消除安装在直线上的杆的布置,因此可以消除复合构件的末端和中间有效协同作用,并且可以消除由于干涉和加强筋的护套引起的拉力降低,从而降低了拉力。传统的抛物线布置具有一种简单,易于有效的结构。

著录项

  • 公开/公告号KR100547485B1

    专利类型

  • 公开/公告日2006-02-01

    原文格式PDF

  • 申请/专利权人

    申请/专利号KR20030033936

  • 发明设计人 노윤근;박상현;장현옥;이상길;

    申请日2003-05-28

  • 分类号E01D21/00;

  • 国家 KR

  • 入库时间 2022-08-21 21:24:20

相似文献

  • 专利
  • 外文文献
  • 中文文献
获取专利

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号