PROBLEM TO BE SOLVED: To provide a lining element for tunnel construction by allowing concrete to be poured into the plural lining elements when the concrete is placed within the lining elements to be used as a tunnel body and a construction method for tunnel lining, using the lining element. ;SOLUTION: The lining element is provided with an earth retaining slide plate 50, slide plates 51, 52 for closing an opening communicating with the outside, and an earth retaining slide plate joint 53. The plate 50, having the above opening and composed in such a hollow box-like manner, can be attached to/detached from a standard element 10 and the like. The joint 53 is extended in the axial direction of the element in the slide plate 50, fitted into another element joint 13, etc., to be connected with the standard element 10, etc., makes the slide plate 50 slid in the axial direction of the element for the purpose of performing attachment/detachment.;COPYRIGHT: (C)2001,JPO