THE CASTING METHOD OF CONCRETE SLAB FOR CONTINUOUS BRIDGE USING BALLAST WAGON
THE CASTING METHOD OF CONCRETE SLAB FOR CONTINUOUS BRIDGE USING BALLAST WAGON
展开▼
机译:压载混凝土浇筑连续桥梁混凝土板的方法
展开▼
页面导航
摘要
著录项
相似文献
摘要
A cast-in-place method of a concrete slab in a continuous bridge using a ballast wagon is provided to place concrete slabs of a continuous bridge continuously, to prevent the excessive stress placed on a steel girder and the crack formation of a concrete slab using a ballast wagon and to utilize for various construction conditions by loading a ballast wagon with various materials such as concrete blocks, soil, sand, gravel, water, etc. A cast-in-place method of a concrete slab in a continuous bridge using a ballast wagon comprises the steps of: installing a steel girder(10) on the whole upper part of each pier(40) in a construction section of a continuous bridge; installing a form traveler(30) and a ballast wagon(50) on the upper part of the steel girder to move along a rail; and placing concrete slabs(20) continuously from an upper part of the steel girder to the other upper part of the steel girder using the form traveler, whereon the ballast wagon is located on a place with occurrence of negative moment ahead of a place with the concrete slabs placed to prevent the transformation of the concrete slab.
展开▼