首页> 外国专利> Structure and Assembly Procedure of Concrete towers for wind turbines, constituted fundamentally by a mounting Procedure of Concrete Towers,The Procedure consists of a pre Assembly and Transport.

Structure and Assembly Procedure of Concrete towers for wind turbines, constituted fundamentally by a mounting Procedure of Concrete Towers,The Procedure consists of a pre Assembly and Transport.

机译:风力涡轮机混凝土塔的结构和组装程序,基本上由混凝土塔的安装程序构成,该程序包括预组装和运输。

摘要

Structure and procedure for erecting concrete towers used in wind turbines in which said towers consist of sections (4) which in turn may each comprise a different number of segments(1) or longitudinal sections. The procedure includes two differentiated cycles, which may take place alongside each other: the pre-assembly of each section of tower and their assembly. The sections may be pre-mounted on bases (5) placed on the ground, with the segment in turn fitted with the help of struts (2) and mechanical jacks (3). This procedure is extremely versatile in that it makes the best logistic use of the material, resources and requisite assembly times since the assembly procedures for each section can be developed alongside each other in the different wind farm towers, and also greater heights can be achieved than is traditionally possible.
机译:用于安装在风力涡轮机中使用的混凝土塔架的结构和程序,其中,所述塔架由部分(4)组成,所述部分(4)又可以分别包括不同数量的部分(1)或纵向部分。该过程包括两个不同的周期,这两个周期可以同时发生:塔的每个部分的预组装及其组装。这些部分可以预先安装在地面上的底座(5)上,而该部分又可以借助支柱(2)和机械千斤顶(3)进行安装。该程序的用途非常广泛,因为它可以在物料,资源和所需的组装时间方面进行最佳的物流使用,因为每个部分的组装程序可以在不同的风电场塔架中同时开发,并且可以实现比传统上是可能的。

著录项

  • 公开/公告号CL2006003095A1

    专利类型

  • 公开/公告日2008-06-20

    原文格式PDF

  • 申请/专利权人 INNEO21 S.L.;

    申请/专利号CL20060003095

  • 申请日2006-11-13

  • 分类号E04H12/00;E04H12/12;E04H12/16;E04H12/34;E04H7/00;E04H7/18;F03D1/00;F03D11/04;

  • 国家 CL

  • 入库时间 2022-08-21 20:08:33

相似文献

  • 专利
  • 外文文献
  • 中文文献
获取专利

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号