Molding Factory for the production of prefabricated concrete Segments for Construction of Towers of Wind Turbine airfoil and Method for the operation of the Factory
Molding Factory for the production of prefabricated concrete Segments for Construction of Towers of Wind Turbine airfoil and Method for the operation of the Factory
展开▼
机译:生产用于制造风力涡轮机翼型塔的预制混凝土节段的模压工厂及其工厂的运营方法
展开▼
页面导航
摘要
著录项
相似文献
摘要
This relates to a Moulding Factory for the production of Precast Concrete Segments for the Construction of a Wind Turbine Towers, the segments of Concrete produced by Molding in that Factory, and to build a Tower of a Wind Turbine To at least partially concrete segments produced by Molding in that Factory,As well as the method of operation of the Factory.Claim 1: Factory (10, 100) Molding for the production of Precast Concrete Segments for the Construction of a Wind Turbine Towers, steel rebar using Passive or active, as well as prestressing Steel, with or without Cement Sheath, and finishing Accessories Inc. This includes the Factory (10, 100) means (30, 30; Lifting means (130) and 26; concreting, 126)Also including the Factory (10, 100): at least one station (14, 114) armed with at least one frame (22, 122), for the preparation of rebar cages; at least one Season (16 concreting; 116), with at least a Mold (24, 124) Steam setting that includes a main body L Mould and countermould, a Canvas Of The Steam Curing.For the implementation of such a rebar Cages in the mold (24, 124), the concreting of the mold (24, 124)The curing of the concrete in the mould (24, 124) and the extraction of the Forged piece (semi fabricated segment (38); 138) from the mold; at least one Season (18; 118) packaging for the finishing of the Stone semi fabricated (38, 138) and / or the implementation of Accessories finish d Stone semi fabricated ICHA (38, 138); and at least one station for storing a collection of segmentsCabadas (32, 132); wherein the Base Station (14, 114) of the Station (16 reinforced concrete; 116) and the Station (18; 118) packaging comprises a Slab of Concrete (28; 128) formed directly on Compacted Ground, i.e., without Foundation, Anchor S or similar Field Compacted, because such means (30,30; 130) elevation are lifts without Foundation, because the body mold is divided into at least two Parties who accompany each other by means of fixing, and because the countermould is divided into at least two Parties who accompany each other by means of fixing NG.Claim 13: exploitation method of Moulding a plant for the production of Precast Concrete Segments for the Construction of Wind Turbine Towers Support agreement with any of the preceding Claims,Characterized in that it includes the following steps: The layout of the factory in a place of origin in disassembled State in initial packets smaller than the segments to produce; the transfer of these initial packets until a location next to the point of delivery of the To produce the Assembly segments; The location of the Factory on the basis of these packagesInitial production of the relevant segments through the factory in assembled State; disassembly in the location of the factory to Factory in a provision of the State removed in final packages smaller segments produced; and the transfer of that S final packages leaving such a Destination Location in conditions basically IGBefore mounting the Hat Factory in that location.
展开▼