首页> 外国专利> Method of estimating the maximum power generation capacity and for controlling a specified power reserve of a single cycle or combined cycle gas turbine power plant, and a power generating system for use with said method

Method of estimating the maximum power generation capacity and for controlling a specified power reserve of a single cycle or combined cycle gas turbine power plant, and a power generating system for use with said method

机译:估计最大发电容量并控制单循环或联合循环燃气轮机发电厂的指定功率储备的方法以及与该方法一起使用的发电系统

摘要

An estimation unit can estimate, on a real-time basis, a maximum power generation capacity of a single cycle or combined cycle gas turbine power plant. For example, the actual power output and the maximum power generation capacity can be calculated relying on a mathematical process model. Subsequently, the calculated actual power output can be compared with the measured power output yielding a model-estimation error. Based on the model-estimation error, a correction signal can be deduced, to correct the calculated maximum power generation capacity. A controller can maintain a specified power reserve. The controller can use an estimate of the maximum power generation capacity as a reference, subtract a load offset, and apply the resulting signal as upper limit of the load set-point.
机译:估计单元可以实时估计单循环或联合循环燃气轮机发电厂的最大发电能力。例如,可以依靠数学过程模型来计算实际功率输出和最大发电容量。随后,可以将计算出的实际功率输出与测量出的功率输出进行比较,从而得出模型估计误差。基于模型估计误差,可以推导出校正信号,以校正计算出的最大发电容量。控制器可以维持指定的功率储备。控制器可以将最大发电容量的估计值用作参考,减去负载偏移,然后将所得信号用作负载设定点的上限。

著录项

  • 公开/公告号US8620482B2

    专利类型

  • 公开/公告日2013-12-31

    原文格式PDF

  • 申请/专利权人 ERIC ANDRE MÜLLER;

    申请/专利号US20100977523

  • 发明设计人 ERIC ANDRE MÜLLER;

    申请日2010-12-23

  • 分类号G05D3/12;G05D5/00;G05D9/00;G05D11/00;G05D17/00;

  • 国家 US

  • 入库时间 2022-08-21 15:59:14