CONSTRUCTION METHOD OF MAIN BRIDGE STRUCTURE USING TEMPORARY COLUMN AND JUNCTION STRUCTURE BETWEEN TEMPORARY COLUMN AND TEMPORARY GIRDER
CONSTRUCTION METHOD OF MAIN BRIDGE STRUCTURE USING TEMPORARY COLUMN AND JUNCTION STRUCTURE BETWEEN TEMPORARY COLUMN AND TEMPORARY GIRDER
展开▼
机译:临时柱与临时梁的交界结构的桥梁主结构施工方法。
展开▼
页面导航
摘要
著录项
相似文献
摘要
PROBLEM TO BE SOLVED: To provide a construction method of main bridge structure and a junction structure between a temporary column and a temporary girder for achieving the same using the temporary column as a bridge structure of a main structure to thereby reduce the construction period and the cost.;SOLUTION: Plural temporary columns 4 are disposed at predetermined intervals and temporary girders are disposed being supported by the plural temporary columns 4, and using the temporary columns 4 and the temporary girders, a bridge body 22 of the main structure is built. After removing the temporary girders, the bridge body 22 and the temporary column 4 are connected to each other being interposed by a joint member 25 between the bridge body 22 and the temporary column 4 to build the main bridge structure 1.;COPYRIGHT: (C)2015,JPO&INPIT
展开▼