The invention relates to a process for consolidating and repairing poles and structure elements made of centrifugally-cast reinforced concrete, in electric lines and sub-stations. According to the invention, the process consists in applying, along the entire height of the pole (9) or structure element, a first layer (2) of fine concrete with a granulation ranging between 0...1 mm, at a thickness varying between 2.5...3.5 mm, after which 1...3 layers (3) of glass fiber cloth are applied with a 20-cm overlap, within an interval of 15...25 cm on the circumference, other fine concrete layers (2) being applied between the cloth layers, followed by a final fine concrete layer (2) and a carbon fiber cloth (4), on a height (a) which, in relation to the pole diameter (b), is in a ratio a/b=3...4.2 from the foundation surface, after which a final fine concrete layer (5) with a thickness ranging between 5...8 mm is applied along the entire pole height, the consolidation being finished by casting a reinforced concrete superfoundation (6) within the perimeter of the existing foundation, on a height (c) which, in relation to the height (a) of the last carbon fiber cloth (4), is in a ratio c/a=0.25...0.36.
展开▼
机译:本发明涉及一种在电力线和变电站中固结和修复由离心浇铸的钢筋混凝土制成的杆和结构元件的方法。根据本发明,该方法包括沿着杆(9)或结构元件的整个高度施加第一层(2)的细混凝土,其细度在0 ... 1mm之间,厚度变化厚度在2.5 ... 3.5毫米之间,然后以15 ... 25厘米的间隔在玻璃上覆盖1 ... 3层(3)20厘米的重叠层,其他细混凝土层(2)施加在布层之间,然后是最终的精细混凝土层(2)和碳纤维布(4),其高度(a)相对于极径(b)为a从基础表面开始的比率a / b = 3 ... 4.2,然后在整个杆高度上施加厚度在5 ... 8毫米之间的最终细混凝土层(5),并通过铸造完成固结在现有基础周长内的钢筋混凝土超基础(6)的高度(c),该高度相对于最后一个碳纤维布(4)的高度(a), c / a = 0.25 ... 0.36
展开▼