PROBLEM TO BE SOLVED: To provide a bar arrangement method in an enlarged-bottom part of a cast-in-place enlarged-bottom pile capable of managing the lower side expansion of a reinforced cage for the enlarged-bottom pile on the ground, and a creation method of the enlarged-bottom pile using the bar arrangement method.;SOLUTION: A reinforcement bar 7 is closed on the side of a hoop nonexistent area part 6, and a reinforced cage 1 for an enlarged-bottom pile is suspended by a suspension member 18, and is lowered in a drilling hole 34 of the ground 35. A body reinforcement part 2 is arranged in a vertical hole 32, and an enlarged-bottom reinforcement part 3 is arranged in an enlarged-bottom hole 34. When pulling up a suspension member 10, a connection part 16 rises in response to rising of a lifting member 9 while being guided by a main reinforcement 4 of the hoop nonexistent area part 6, and a support reinforcement 11 pushes out the connection part 17 to the outside in the radial direction of the hoop nonexistent area part 6. Since the reinforcement bar 7 is expanded in an enlarged-bottom shape to the outer side in the radial direction than the hoop nonexistent area part 6 with the connection part 8 as the rotational center via a support reinforcement 11, an operator can manage the expansion of the reinforcement bar 7 by confirming a pull-up quantity of the suspension member 10 on the ground. After this bar arrangement method, concrete is poured into the drilling hole, so that an enlarged-bottom part becomes planned strength.;SELECTED DRAWING: Figure 1;COPYRIGHT: (C)2017,JPO&INPIT
机译:解决的问题:提供一种在现场浇筑的扩底桩的扩底部分中进行钢筋布置的方法,该方法能够管理地面上扩底桩的钢筋笼的下侧膨胀,以及解决方案:解决方案:在不存在箍的区域部分6的侧面上封闭一根钢筋7,并用一根吊杆将一根用于悬底桩的钢筋笼1悬挂起来。悬架构件18,并降低到地面35的钻孔34中。主体加强部分2布置在竖直孔32中,并且底底加强部分3布置在底底孔34中。在悬架部件10上,连接部分16响应于提升部件9的上升而上升,同时被箍不存在区域部分6的主加强件4引导,支撑加强件11将连接部分17推出到外部在径向方向上箍筋不存在区域部分6的n,通过以支撑部8为旋转中心,使加强筋7以箍筋不存在区域部分6为中心,比箍箍不存在区域部分6在径向外侧扩大。如图11所示,操作员可以通过确认悬吊构件10在地面上的上拉量来管理加强杆7的膨胀。采用这种钢筋布置方法后,将混凝土倒入钻孔中,以便使底部扩大的部分成为计划的强度。;选定的图纸:图1;版权:(C)2017,JPO&INPIT

著录项

  • 公开/公告号JP2017166278A

    专利类型

  • 公开/公告日2017-09-21

    原文格式PDF

  • 申请/专利权人 KUMAGAI GUMI CO LTD;

    申请/专利号JP20160054984

  • 发明设计人 MORI TOSHIHIRO;

    申请日2016-03-18

  • 分类号E02D5/44;E02D5/34;

  • 国家 JP

  • 入库时间 2022-08-21 14:01:37

相似文献

  • 专利
  • 外文文献
  • 中文文献
获取专利

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号