Method for low load operation of a power plant with a once-through boiler
Method for low load operation of a power plant with a once-through boiler
展开▼
机译:具有直通式锅炉的发电厂低负荷运行的方法
展开▼
页面导航
摘要
著录项
相似文献
摘要
The once-through boiler includes a water supply and at least an economizer, an evaporator superheater. No valves are provided between the economizer, the evaporator and the superheater. The high-pressure turbine includes a control valve. The method for low load operation of a power plant with a once-through boiler and a high pressure turbine includes providing a parameter indicative of the stable operation of the once-through boiler in once-through operation, and on the basis of this parameter adjusting the control valve in order to regulate the pressure within the economizer and evaporator and/or adjusting the temperature of the water supplied to the economizer.