The invention relates to a method for establishing a transformer platform with at least four piles (12) by exactly one pile driver (1) is spent on location, the pile driver (1) on the seabed (9) by means of extendable support legs (7) is supported on or on the piling device (1) Rammschablonen (11) are mounted, the piles (12) are plugged through their assigned Rammschablonen (11), the piles (12) successively while maintaining the position of Rammgerätes (1) in the seabed (9 ) are rammed, upper ends of the in the seabed (9) rammed piles (12) at the level or above the associated Rammschablone (11) are arranged, the support legs (7) of the pile driver (1) are retracted and the pile driver (1) of the location is spent away.