摘要

The present invention can be reliably excavated while minimizing the deformation of the track while minimizing the deformation of the ground while maintaining the existing railway track and railway operation, and after the construction of bridges and piers after excavation, it is possible to install girders and slabs. It provides a method for constructing railway bridges that maintains existing railway tracks and railway operations. A method for constructing a railway bridge under an existing railroad track according to a preferred embodiment of the present invention includes the steps of: (a) inserting a rail support between rails supporting rails in a certain section of the railroad track; (b) arranging the rail support beams on both sides of the railroad track, and then binding both ends of the rail support to the rail support beams; (c) placing two or more support piles in a lengthwise direction of the railroad track 20 at a predetermined distance from the rail support connecting beams to penetrate the ground to a certain depth; (d) fixing the cap beam on the top of the support pile; (e) installing a plurality of support jacks on the upper surface of the cap beam; (f) arranging a plurality of cross beams orthogonally in the lower portion of the railroad line to pass through the upper end of the support jack, and fixing the cross beam to the support jack; (g) manipulating the support jack to allow the cross beam to support the rail support beam; (h) After the steps (c) to (g) are performed at two or more places in a certain section of the railroad track 20 to stably support the railroad track, stepwise to the excavation floor targeting the lower part of the railroad track. Excavating; (i) mounting the bridge girder in the space between the railway track and the shift and pier after completing the shift and pier construction at the planned location on the excavated floor; (j) the step of constructing a floor plate by pouring concrete on top of the bridge girder; characterized in that it is constructed including.
机译:在保持现有的铁路轨道和铁路运营的同时,在使轨道的变形最小化同时使地面的变形最小化的同时,能够可靠地进行本发明的挖掘,并且在挖掘后的桥梁和桥墩的建造之后,可以安装梁和平板。它提供了一种维护现有铁路轨道和铁路运营的铁路桥梁建造方法。根据本发明的优选实施例的在现有铁轨下建造铁路桥梁的方法包括以下步骤:(a)在铁轨的特定部分中的铁轨支撑轨之间插入铁轨支撑; (b)将铁轨支撑梁布置在铁轨的两侧,然后将铁轨支撑的两端绑到铁轨支撑梁上; (c)在铁轨20的长度方向上与铁轨支撑连接梁相距预定距离放置两个或更多个支撑桩,以穿透地面至一定深度; (d)将顶梁固定在支撑桩的顶部; (e)在顶梁的上表面安装多个支撑千斤顶; (f)在铁路线的下部正交地布置多个横梁,以穿过支撑千斤顶的上端,并将该横梁固定至支撑千斤顶; (g)操纵支撑千斤顶以允许横梁支撑轨道支撑梁; (h)在铁轨20的特定部分中的两个或更多个位置执行步骤(c)至(g)以稳定地支撑铁轨之后,逐步到达以铁轨下部为目标的挖掘地面。发掘(i)在挖掘的地面上的规划位置完成了平移和桥墩的建造之后,在铁路轨道和平移和桥墩之间的空间中安装桥梁; (j)通过在桥梁的顶部浇筑混凝土来建造地板的步骤;其特征在于构造包括。

著录项

  • 公开/公告号KR102105230B1

    专利类型

  • 公开/公告日2020-04-27

    原文格式PDF

  • 申请/专利权人 주식회사 포스코건설;

    申请/专利号KR20170123291

  • 发明设计人 정영도;김영필;전진택;김동완;

    申请日2017-09-25

  • 分类号E01D18;E01D19/02;E01D19/10;E01D21;E02D27/32;

  • 国家 KR

  • 入库时间 2022-08-21 11:04:47

相似文献

  • 专利
  • 外文文献
  • 中文文献
获取专利

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号