Development and testing of industrial scale, coal-fired combustion system, Phase 3. Nineteenth quarterly technical progress report, July 1, 1996--September 30, 1996

机译:工业规模,燃煤燃烧系统的开发和测试,第3阶段。第19次季度技术进步报告,1996年7月1日 - 1996年9月30日

获取原文

摘要

In the third quarter of calendar year 1996, 13 days of combust-boiler tests were performed, including 3 days of tests on a parallel DOE sponsored project on sulfur retention in a stagging combustor. Between tests, modifications and improvements that were indicated by these tests were implemented. This brings the total number of test days to the end of September in the task 5 effort to 41, increased to 46 as of the date of this Report, 10/27/96. This compares with a total of 63 test days needed to complete the task 5 test effort. As reported previously, the only major modification to the Williamsport combustor has been the addition of a new downstream section, which lengthens the combustor and improves the combustor-boiler interface. The original combustor section, which includes the fuel, air, and cooling water delivery systems remained basically unchanged. Only the refractory liner was completely replaced, a task which occurs on an annual basis in all commercial stagging utility combustors. Therefore, this combustor has been operated since 1988 without replacement.

著录项

相似文献

  • 外文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号