首页> 美国政府科技报告 >Review of the Cost Estimate and Schedule for the 2240-MWt High-Temperature Gas-Cooled Reactor Steam-Cycle/Cogeneration Lead Plant.
【24h】

Review of the Cost Estimate and Schedule for the 2240-MWt High-Temperature Gas-Cooled Reactor Steam-Cycle/Cogeneration Lead Plant.

机译:2240-mWt高温气冷堆蒸汽循环/热电联产铅厂的成本估算和进度评述。

获取原文

摘要

This report documents Bechtel's review of the cost estimate and schedule for the 2240 MWt High Temperature Gas-Cooled Reactor Steam Cycle/Cogeneration (HTGR-SC/C) Lead Plant. The overall objective of the review is to verify that the 1982 update of the cost estimate and schedule for the Lead Plant are reasonable and consistent with current power plant experience. (ERA citation 09:004631)