The decommissioning programme at Agesta started in 2020 and is due to be finalised in 2025.Clearance measurements have already been completed for the cooling tower, turbine building, control room and switchgear building, and the cooling tower has been demolished.Inside the controlled zone, other D&D activities are under way: removal of reactor internals and RPV; removal of other systems; and equipment decontamination which has been ongoing during the whole decommissioning period. The control rod cutting was the third major project to be completed. The next large project will be reactor pressure vessel and internals in situ segmentation. Preparatory work is under way on site, and first segmentation is planned in early 2022.