Beam commissioning and operation of the Japan Proton Accelerator Research Complex 3-GeV rapid cycling synchrotron

机译:日本质子加速器研究中心3-GeV快速循环同步加速器的光束调试和运行

获取原文
           

摘要

The 3-GeV rapid cycling synchrotron (RCS) of the Japan Proton Accelerator Research Complex (J-PARC) is a high-power pulsed proton driver aiming at 1?MW output beam power. The RCS was beam commissioned in October 2007 and made available for user operation in December 2008 with an output beam power of 4?kW. Since then, the output beam power of the RCS has been steadily increasing following progressions in beam tuning and hardware improvements. So far, the RCS has successfully achieved high-intensity beam trials of up to 420?kW at a low-level intensity loss of less than 1%, and the output beam power for the routine user program has been increased to 210?kW. The most important issues in increasing the output beam power are the control and minimization of beam loss to maintain machine activation within the permissible level. This paper presents the current status of the RCS beam power ramp-up, with particular emphasis on our approach to beam loss issues. The future prospects of RCS beam commissioning and operation are also described.
机译:日本质子加速器研究中心(J-PARC)的3-GeV快速循环同步加速器(RCS)是一种高功率脉冲质子驱动器,目标输出功率为1?MW。 RCS于2007年10月进行了光束调试,并于2008年12月投入用户使用,输出光束功率为4kW。从那时起,随着光束调整和硬件改进的发展,RCS的输出光束功率一直稳定增长。到目前为止,RCS已成功完成了高达420?kW的高强度光束试验,而低水平的强度损失不到1%,并且常规用户程序的输出光束功率已提高至210?kW。增加输出光束功率最重要的问题是控制和最小化光束损失,以将机器激活保持在允许的水平内。本文介绍了RCS光束功率提升的当前状态,尤其着重于我们解决光束损耗问题的方法。还描述了RCS光束调试和运行的未来前景。

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号