The 800MW Vineyard Wind project has been delayed as a result of a federal review into offshore wind's impact on the US. Will the sector ever truly take off in the country? Vineyard needs a final environmental impact statement (FEIS) from the US government's Bureau of Ocean Energy Management (BOEM) to proceed. It had been expected in April, before BOEM declared in June it would carry out another review into the project. Now, in a surprise announcement, BOEM said it would expand the review to include other wind projects in the region with power purchase agreements (PPAs).This means 0rsted and Eversource's 130MW South Fork and 704MW Revolution developments, both off Rhode Island.
展开▼
机译:由于对海上风电对美国的影响进行联邦审查,导致800MW葡萄园风电项目被推迟。该行业会在该国真正腾飞吗?葡萄园需要美国政府海洋能源管理局(BOEM)的最终环境影响声明(FEIS)才能进行。预期在4月,BOEM在6月宣布它将对该项目进行另一次审查。现在,在一个令人惊讶的公告中,BOEM表示将扩大审查范围,使其包括该地区其他具有电力购买协议(PPA)的风能项目,这意味着0rsted和Eversource在罗德岛附近的130MW South Fork和704MW Revolution开发项目。