Using a detailed inventory of a large wastewater treatment plant to estimate the relative importance of construction to the overall environmental impacts

机译:使用大型废水处理厂的详细清单来估算建筑对整体环境影响的相对重要性

获取原文
获取原文并翻译 | 示例
           

摘要

The aim of this work is to quantify the relative contribution to the overall environmental impact of the construction phase compared to the operational phase for a large conventional activated sludge wastewater treatment plant (WWTP). To estimate these environmental impacts, a systematic procedure was designed to obtain the detailed Life Cycle Inventories (LCI) for civil works and equipment, taking as starting point the construction project budget and the list of equipment installed at the Girona WWTP, which are the most reliable information sources of materials and resources used during the construction phase. A detailed inventory is conducted by including 45 materials for civil works and 1,240 devices for the equipment. For most of the impact categories and different life spans of the WWTP, the contribution of the construction phase to the overall burden is higher than 5% and, especially for metal depletion, the impact of construction reaches 63%. When comparing to the WWTP inventories available in Ecoinvent the share of construction obtained in this work is about 3 times smaller for climate change and twice higher for metal depletion. Concrete and reinforcing steel are the materials with the highest contribution to the civil works phase and motors, pumps and mobile and transport equipment are also key equipment to consider during life cycle inventories of WWTPs. Additional robust inventories for similar WWTP can leverage this work by applying the factors (kg of materials and energy per m(3) of treated water) and guidance provided. (C) 2017 Elsevier Ltd. All rights reserved.
机译:这项工作的目的是量化与大型常规活性污泥废水处理厂(WWTP)的运营阶段相比,建设阶段对整体环境影响的相对贡献。为了估算这些环境影响,设计了系统的程序来获取土建工程和设备的详细生命周期清单(LCI),以建设项目预算和赫罗纳污水处理厂安装的设备清单为起点,这是最施工阶段所用材料和资源的可靠信息来源。通过包括45种用于土建工程的材料和1,240种设备的设备来进行详细的清点。对于污水处理厂的大多数影响类别和不同寿命,施工阶段对总体负担的贡献高于5%,尤其是对于金属耗竭,施工影响达到63%。与Ecoinvent中可用的WWTP存量进行比较时,这项工作中获得的建筑份额因气候变化而减少了约3倍,而因金属消耗而减少了约2倍。混凝土和钢筋是对土建工程阶段贡献最大的材料,电动机,泵,移动和运输设备也是污水处理厂生命周期清单中要考虑的关键设备。类似的污水处理厂的其他强大清单可以通过应用因素(所处理的水每m(3)的材料和能量的千克)和提供的指导来利用这项工作。 (C)2017 Elsevier Ltd.保留所有权利。

著录项

  • 来源
    《Water Research》 |2017年第1期|614-623|共10页
  • 作者单位

    Univ Girona, Inst Environm, LEQUIA, Campus Montilivi,Carrer Maria Aurelia Capmany 69, E-17003 Girona, Catalonia, Spain;

    Univ Girona, Catalan Inst Water Res, ICRA, Sci & Technol Pk,Emili Grahit 101, E-17003 Girona, Spain;

    Univ Girona, Inst Environm, LEQUIA, Campus Montilivi,Carrer Maria Aurelia Capmany 69, E-17003 Girona, Catalonia, Spain;

    Univ Girona, Inst Environm, LEQUIA, Campus Montilivi,Carrer Maria Aurelia Capmany 69, E-17003 Girona, Catalonia, Spain;

    Univ Girona, Inst Environm, LEQUIA, Campus Montilivi,Carrer Maria Aurelia Capmany 69, E-17003 Girona, Catalonia, Spain|Univ Girona, Catalan Inst Water Res, ICRA, Sci & Technol Pk,Emili Grahit 101, E-17003 Girona, Spain;

  • 收录信息 美国《科学引文索引》(SCI);美国《工程索引》(EI);
  • 原文格式 PDF
  • 正文语种 eng
  • 中图分类
  • 关键词

    Civil works; Equipment; LCA; Life span; WWTP; Detailed inventory;