The temporary beam support shown in the drawing (left) reduced our cost by a day of labor. For contractors these days, this is a big deal, especially on a small job like this one. Here's how it worked. A typical deck project begins by digging the holes for the footings, getting them inspected, then placing the concrete. We tweaked this sequence by putting the forms in place on day one and by continuing with our framing by supporting the beam with the temporary braces shown in the drawing. The posts are measured and cut to fit, and are hung from the beam with the base and cap hardware already attached.
机译:图中所示的临时梁支撑(左)减少了一天的劳动量。对于如今的承包商而言,这是一件大事,尤其是在像这样的小型工作上。这是它的工作方式。一个典型的甲板工程开始于为基础挖出孔,对其进行检查,然后放置混凝土。我们通过在第一天将模板放置在适当位置并通过用图中所示的临时支撑支撑梁来继续进行框架来调整此顺序。对立柱进行测量和切割以使其适合,并在已经安装了基座和盖硬件的情况下将其悬挂在梁上。

著录项

  • 来源
    《Fine Homebuilding》 |2011年第218期|p.22|共1页
  • 作者

    BRIAN BROPHY;

  • 作者单位
  • 收录信息
  • 原文格式 PDF
  • 正文语种 eng
  • 中图分类
  • 关键词

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号