Remediation Of Pcb Contaminated Soils In The Canadian Arctic: Excavation And Surface Prb Technology

机译:修复加拿大北极受Pcb污染的土壤:开挖和表面Prb技术

获取原文
获取原文并翻译 | 示例

摘要

The site BAF-5 is located on the summit of Resolution Island,Nunavut,just southeast of Baffin Island at 61° 35'N and 60° 40'W.The site was part of a North American military defense system established in the 1950s that became heavily contaminated with PCBs during and subsequent,its operational years.Remediation through excavation of the PCB contaminated soil at Resolution Island began in 1999 and at its completion in 2006 approximately 5 tonnes of pure PCBs in approximately 20,000 m~3 of soil were remediated.Remediation strategies were based on both quantity of soil and level of contamination in the soil.Excavation removed 96% of the PCB contaminated soil on site.In 2003,a surface funnel-and-gate permeable reactive barrier was design and constructed to treat the remaining contamination left in rock crevices and inaccessible areas of the site.Excavation had destabilized contaminated soil in the area,enabling contaminant migration through erosion and runoff pathways.The barrier was designed to maximize sedimentation through settling ponds.This bulk removal enabled the treatment of highly contaminated fines and water through a permeable gate.The increased sediment loading during excavation required both modifications to the funnel and a shift to a more permeable,granular system.Granulated activated charcoal was chosen for its ability to both act as a particle retention filter and adsorptive filter.The reduction in mass of PCB and volume of soils trapped by the funnel of the barrier indicate that soils are re-stabilizing.In 2007,nonwoven geotextiles were re-introduced back into the filtration system as fine filtering could be achieved without clogging.Monitoring sites downstream indicate that the barrier system is effective.This paper describes the field progress of PCB remediation at Resolution Island.
机译:BAF-5基地位于努芬武特的决议岛顶峰,就在巴芬岛东南方,北纬61°35'和西经60'40°。该站点是1950年代建立的北美军事防御系统的一部分从1999年开始对决议岛进行PCB污染土壤的挖掘修复,并于2006年竣工,对约20,000 m〜3的土壤中约5吨纯PCB进行了修复。修复策略基于土壤的数量和土壤中的污染水平。开挖现场清除了96%的多氯联苯污染土壤。2003年,设计并建造了一个表面漏斗和门可渗透的反应性屏障,用于处理剩余的污染物污染物残留在岩石缝隙和无法进入的区域中。开挖使该区域的污染土壤不稳定,使污染物能够通过侵蚀和径流途径迁移。为了使沉淀池中的沉淀物最大化,这种大量去除可以通过一个可渗透的闸门处理高度污染的细粉和水。在挖掘过程中增加的沉淀物负荷既需要对漏斗进行改造,又需要转变为更具渗透性的粒状系统。选择木炭是因为它既能起到颗粒保留过滤器的作用,又能起到吸附过滤器的作用.PCB的质量降低和被屏障漏斗捕获的土壤量减少表明土壤正在重新稳定.2007年,非织造土工布被重新使用引入到过滤系统中,因为可以实现精细过滤而不会发生堵塞。下游的监测点表明隔离系统是有效的。本文介绍了Resolution Island上PCB修复的现场进展。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号