Arecent case of the California Court of Appeal Second District confirmed what had always been the law. In order for anyone other than design professionals, to have a right to a mechanic's lien, construction must start. In April of 2001, the owner entered into an agreement with a licensed contractor for the construction of a project. In the next two years, the contractor provided approximately $850,000 in design-related services. He did design, planning, and hired design professionals. The owner tried to obtain financing, without success. Therefore, construction never started. No building permit was every issued for the project. No actual visual construction or other work was conducted at the site by anyone.
机译:加利福尼亚第二上诉法院的Arecent案确认了以往的法律。为了使除设计专业人员以外的任何人都有权获得机械师的留置权,必须开始建造。在2001年4月,业主与一家持牌承包商签订了建设项目的协议。在接下来的两年中,承包商提供了约85万美元的设计相关服务。他从事设计,规划和雇用设计专业人员。所有者试图获得融资,但没有成功。因此,建设从未开始。没有为该项目签发任何建筑许可证。任何人都没有在现场进行实际的视觉构造或其他工作。

著录项

  • 来源
    《Reeves journal》 |2005年第2期|p.8|共1页
  • 作者

    Sam K. Abdulaziz;

  • 作者单位

    Abdulaziz & Grossbart, P.O. Box 15458, North Hollywood, CA 91615-5458;

  • 收录信息
  • 原文格式 PDF
  • 正文语种 eng
  • 中图分类 建筑科学;
  • 关键词

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号