In 2009, remediation began for a nonoperational fuel-cycle facility previously used for government contract work. Between 2009 and spring of 2011, the work consisted of remediating several areas of uranium-impacted soil, decontamination and demolition of two impacted building structures (including the slab and underlying process piping and utilities), and removing more than 1100 meters of buried waste line piping. Late in the spring of 2011, the last phase of remediation commenced: removal and offsite disposal of uranium-impacted sediments from portions of an approximately 1200-m-long gaining stream known as the "Site Brook." In November 2011, the remediation and restoration of Site Brook was comolete.
展开▼
机译:2009年,开始对以前用于政府合同工作的非运行燃料循环设施进行补救。在2009年至2011年春季之间,工作包括对受铀影响的土壤进行修复,对两个受影响的建筑结构(包括楼板和下层工艺管道及公用设施)进行净化和拆除,并清除了1100多米的掩埋式废物管线管道。 2011年春末,补救工作的最后一个阶段开始了:从大约1200米长的增流中被称为“ Site Brook”的部分中除去和离场处理受铀污染的沉积物。 2011年11月,对Site Brook的修复和恢复工作进行了。
展开▼