Load-carrying capacity of flooded masonry arch bridges

机译:淹没的砌体拱桥的承载能力

获取原文
获取原文并翻译 | 示例
           

摘要

Many existing codes of practice for masonry arch bridge assessment fail to provide engineers with adequate guidance on the adverse effects that saturated environmental or flood conditions are likely to have on load-carrying capacity. Analysis indicates that the load-carrying capacity of a fully flooded arch bridge backfilled with cohesionless fill could typically be reduced by a factor of 1.6-1.8, or even more in specific circumstances. The significant influence of flooding on load-carrying capacity has now been verified using small-scale experiments which are described in the paper. The effects of flooding on waterproofed and unwaterproofed bridges are also analysed numerically and the circumstances under which capacity reductions are likely to be highest are identified. This paper should be useful to engineers dealing with bridges which are at risk of flooding.
机译:许多现有的砌体拱桥评估实践准则未能为工程师提供充分的指导,以应对饱和的环境或洪水条件可能对承重能力产生的不利影响。分析表明,用无粘性填充物回填的全淹没拱桥的承载能力通常会降低1.6-1.8倍,在特定情况下甚至会降低更多。现在已经使用本文中描述的小规模实验验证了洪水对承载能力的重大影响。还对洪水对防水和非防水桥梁的影响进行了数值分析,并确定了容量减少可能最大的情况。本文对于处理有洪水风险的桥梁的工程师应该是有用的。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号