A US$345 million project to upgrade and extend Shanghai's sewerage system was completed in 2007. The tunnelled component of this scheme includes 30 km of sewer tunnels with diameters varying from 2·4 to 3·5 m i.d.—a major tunnelling project in its own right. When methane gas was encountered during construction of the twin-bore 2 4 m i.d. outfall tunnel, the client recognised the serious safety implications and, being keen to complete the works without incident, requested expert advice from both national and international experts. This paper demonstrates knowledge sharing and the application of best practice in China through a case study of how the client, in partnership with national and international experts, dealt with the methane problem, enabling the outfall tunnels to be constructed without incident despite the onerous ground conditions. This case study must be viewed in the context of the absolute need for the development of Shanghai wastewater facilities with knowledge of the difficulties experienced in earlier similar projects.
机译:一项价值3.45亿美元的用于升级和扩展上海污水处理系统的项目已于2007年完成。该计划的隧道部分包括30公里长的污水管道,直径从2·4到3·5 mid不等,这是其自身的一项重大隧道工程。对。在双孔的建造过程中遇到甲烷气体2 4 m。客户了解到泄洪洞的严重安全隐患,并热衷于完成工程而不会发生事故,因此请国家和国际专家提供专家意见。本文通过案例研究来说明客户如何与国内和国际专家合作解决甲烷问题,从而尽管在地面条件恶劣的情况下也能在没有事故的情况下建造出水隧道,但该案例展示了知识共享和最佳实践在中国的应用。该案例研究必须在绝对需要上海污水处理设施开发的背景下进行,并且要了解早期类似项目所遇到的困难。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号