Tunnelling and compensation grouting at Bond Street, London

机译:伦敦邦德街的隧道和补偿灌浆

获取原文
获取原文并翻译 | 示例

摘要

As part of the London Underground Bond Street station upgrade works, a Costain, Laing O'Rourke and London Underground One team is constructing over 450m of tunnels using the sprayed concrete lining method. The risk of damage to overlying listed buildings from tunnel-induced settlement was mitigated through, among other measures, the use of compensation grouting. Installation of the compensation grouting array was observed to coincide with settlements of over 10 mm. The source of the settlement is attributed to the wet flush open bore method employed to install the tubes a manchettes. Subsequent heave and building settlements are correlated with changes in pore pressures beneath the array following grouting and tunnelling excavation phases, respectively. It is demonstrated that grouting causes large pore pressure increases which, while dissipating, coincide with 'relaxation' settlements. Analysis of surface and subsurface settlements indicates that the staged construction of a large-diameter tunnel reduces the ultimate volume losses. Deformations of the tunnel lining following spraying exceeded 25 mm, although this could not be directly attributed to compensation grouting.
机译:作为伦敦地铁邦德街站升级工程的一部分,Costain,Laing O'Rourke和伦敦地铁一队正在使用喷射混凝土衬砌法建造超过450m的隧道。通过采用补偿灌浆等措施,减轻了因隧道诱发的沉降而对上层建筑造成损坏的风险。观察到补偿灌浆阵列的安装与超过10毫米的沉降一致。沉降的来源归因于湿冲洗开孔方法,该方法用于将金属薄片安装在铁棍上。随后的沉沉和建筑物沉降分别与灌浆和隧道开挖阶段之后阵列下方的孔隙压力变化相关。事实证明,灌浆会导致大的孔隙压力增加,而在消散的同时与“松弛”沉降相吻合。对地表和地下沉降的分析表明,大直径隧道的分段施工可减少最终的体积损失。喷涂后隧道衬砌的变形超过25毫米,尽管这不能直接归因于补偿灌浆。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号