PLL had commissioned its 5 MMTPA LNG receiving and re-gasification terminal (the first in the country) at Dahej — Gujarat (built at the cost of approximately US$550 million) in February 2004, and expansion of the same to handle 10 MMTPA LNG was also completed in March 2009, currently at an advanced stage in doubling its capacity. PLL has also commenced the construction work for its second LNG receiving and re-gasification terminal (2.5 MMTPA expandable to 5 MMTPA) at Kochi, Kerala in Feb 2008.
机译:PLL于2004年2月在位于古吉拉特邦Dahej的5个MMTPA LNG接收和再气化终端(该国第一座)投产(造价约5.5亿美元),并扩建了处理10个MMTPA LNG的终端。于2009年3月完工,目前正处于产能翻倍的高级阶段。 PLL还于2008年2月在喀拉拉邦高知开始了其第二个LNG接收和再气化终端(2.5 MMTPA扩展到5 MMTPA)的建设工作。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号