The olkiluoto-3 reactor pressure vessel was installed on June 18. The operation was completed two weeks after the plant owner, Finland's Teollisuuden Voima Oyj (TVO), confirmed that the reactor will not begin producing electricity until 2013 (see page 49, this issue). The original date for the start of operation of the reactor, the first of Areva's EPR design to be constructed, was 2009.rnAccording to Areva, the pressure vessel, which weighs 420 metric tons and measures 5.3 m in diameter and 10.6 m in height, was transported from its storage hangar at the site to just outside the reactor containment and then was lifted into the reactor building and placed into the reactor pit. The next components to be installed will be the reactor coolant piping and the housings of the main reactor coolant pumps. The first of the four steam generators will be installed toward the end of the summer, and the other steam generators and the pressurizer should be installed by the end of the year. The main components of the turbine island have already been installed.
机译:olkiluoto-3反应堆压力容器已于6月18日安装。工厂所有人芬兰的Teollisuuden Voima Oyj(TVO)确认反应堆要到2013年才开始发电,此作业已完成两周。 )。反应堆开始运行的最初日期是阿海珐公司首次建造的EPR设计,定于2009年。根据阿海珐公司的报道,压力容器重420公吨,直径为5.3 m,高度为10.6 m,将其从现场的存储机库运输到反应堆安全壳外,然后被提升到反应堆建筑物中并放入反应堆坑中。接下来要安装的组件将是反应堆冷却剂管道和主要反应堆冷却剂泵的壳体。四个蒸汽发生器中的第一个将在夏季末安装,其他蒸汽发生器和加压器应在年底安装。涡轮机岛的主要组件已经安装。

著录项

  • 来源
    《Nuclear news 》 |2010年第8期| P.17-1867-68| 共4页
  • 作者

  • 作者单位
  • 收录信息
  • 原文格式 PDF
  • 正文语种 eng
  • 中图分类
  • 关键词

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号