首页> 外文期刊>Nuclear Engineering and Design >An analysis for risk impact of Emergency Diesel Generator on modified Surveillance Test Interval by considering failure due to demand stress
【24h】

An analysis for risk impact of Emergency Diesel Generator on modified Surveillance Test Interval by considering failure due to demand stress

机译:考虑需求压力导致的故障,分析应急柴油发电机组对改进的监控测试间隔的风险影响

获取原文
获取原文并翻译 | 示例
           

摘要

The common practice for the estimation of the probability of a component failure to start on demand is to lump together standby failures and failures due to the stress induced by the demand itself. In this paper, a failure by demand stress as well as a standby failure is considered separately to estimate the probability of a failure on demand when a Surveillance Test Interval (STI) is modified. The proposed estimation method is based on a, the ratio of the probability of a failure by demand stress to that of a failure on demand. The estimate of a, however, should be changed when an STI is modified. An estimation method for a', the changed parameter corresponding to a under an STI modification is also suggested. With the proposed estimation method and the estimate of a' from a plant specific database, a risk impact analysis due to an STI modification for the Emergency Diesel Generator (EDG) of UCN units 3 and 4 is performed. From the sensitivity analysis, the following conclusions can de derived: if it is assumed that all failures occur during the standby time, as it is the case in the common practice, the results can overestimate the risk impact. And it is required to construct a component reliability database containing detailed information on the failure types to recognize whether a component failure occurs during a standby time or a test.
机译:估计组件故障按需启动的可能性的常用方法是将备用故障和由于需求本身引起的压力而导致的故障集中在一起。在本文中,当修改了监视测试间隔(STI)时,将分别考虑由需求压力引起的故障和备用故障,以估计按需故障的可能性。所提出的估计方法基于需求应力导致的故障概率与按需故障的概率之比。但是,当修改STI时,应更改a的估计值。还提出了一种针对a'的估计方法,其是在STI修改下对应于a的改变后的参数。利用所提出的估计方法和来自工厂特定数据库的a'估计,由于UCN单元3和4的应急柴油发电机(EDG)进行了STI修改而进行了风险影响分析。从敏感性分析中,可以得出以下结论:如果假定所有故障都在备用时间内发生,就像通常的做法那样,那么结果可能会高估风险影响。并且需要构造一个包含有关故障类型的详细信息的组件可靠性数据库,以识别在备用时间内还是在测试期间发生了组件故障。

著录项

  • 来源
    《Nuclear Engineering and Design》 |2010年第10期|p.3577-3581|共5页
  • 作者单位

    Integrated Safety Assessment Division, Korea Atomic Energy Research Institute, Probabilistic Safety Assessment Division, 1045 Deadeok-daero, P.O. Box 105, Yusong-Cu, Daejeon 305-600, Republic of Korea;

    Dept. of Statistics, Chungnam National University, 220 Cung-dong, Yusung-gu, Daejeon 305-764, Republic of Korea;

    Integrated Safety Assessment Division, Korea Atomic Energy Research Institute, Probabilistic Safety Assessment Division, 1045 Deadeok-daero, P.O. Box 105, Yusong-Cu, Daejeon 305-600, Republic of Korea;

  • 收录信息 美国《科学引文索引》(SCI);美国《工程索引》(EI);美国《生物学医学文摘》(MEDLINE);
  • 原文格式 PDF
  • 正文语种 eng
  • 中图分类
  • 关键词