Emergency Response and Back Analysis of the Failures of Earthquake Triggered Cascade Landslide Dams on the Mianyuan River, China

机译:绵源河地震诱发的梯级滑坡大坝失灵的应急响应与反分析

获取原文
获取原文并翻译 | 示例
           

摘要

This study has reviewed the emergency action and drainage process of the Xiaogangjian, Xiaogangjian-lower, and Yibadao cascade landslide dams that were formed during the 2008 Wenchuan earthquake in China's southwest Sichuan Province. In order to minimize the hazards caused by the dam breach flood, mitigation works were carried out. Using underwater explosion and mechanical excavation, the dam heights of Xiaogangjian and Yibadao were lowered by 8 and 5m, respectively. On June 12, the Xiaogangjian Dam was overtopped, followed by the failures of the two downstream dams, resulting in a flood with a peak discharge of 3,950m3/s measured at the downstream Hanwang gauge station. This paper describes the geographic and geotechnical features, mainly obtained from the field survey and laboratory testing. The back analysis on the breach flood is based on the authors' work on Tangjiashan and Yigong barrier lakes. The results of this study show that the measured breach flood hydrograph can be reproduced using the currently available analytical methods if the input parameters related to the soil erosion and geotechnical properties are well determined based on experience and laboratory testing. The results of the analysis also show that the mitigation works of lowering the Xiaogangjian and Yibadao dam crest elevations effectively reduced the peak flow by nearly 20%.
机译:这项研究回顾了在中国西南部四川省2008年汶川地震期间形成的小港尖,小港尖下游和宜坝岛梯级滑坡坝的应急行动和排水过程。为了最大程度地减少大坝溃坝洪水带来的危害,开展了缓解工程。通过水下爆炸和机械开挖,小港尖和一坝岛大坝高度分别降低了8m和5m。 6月12日,小港尖大坝超顶,随后两个下游大坝发生故障,导致洪水,在下游汉王水位站测得的峰值流量为3,950m3 / s。本文介绍了地理和岩土特征,主要是从现场调查和实验室测试中获得的。关于突破洪水的反向分析是基于作者在唐家山和义工屏障湖上所做的工作。这项研究的结果表明,如果根据经验和实验室测试很好地确定了与土壤侵蚀和岩土特性有关的输入参数,则可以使用当前可用的分析方法来复制测得的违规洪水水位图。分析结果还表明,降低小港尖和宜坝岛大坝坝顶高程的缓解措施有效地减少了峰值流量近20%。

著录项

  • 来源
    《Natural Hazards Review》 |2018年第3期|05018005.1-05018005.12|共12页
  • 作者单位

    State Key Lab Simulat & Regulat Water Cycle River, Beijing 100048, Peoples R China;

    China Inst Water Resources & Hydropower Res, Dept Geotech Engn, Beijing 100048, Peoples R China;

    Anrong Construct Corp, Engn, 4 Anrong St, Chengdu 611135, Sichuan, Peoples R China;

    State Key Lab Simulat & Regulat Water Cycle River, Beijing 100048, Peoples R China;

    Tsinghua Univ, State Key Lab Hydrosci & Hydraul Engn, Beijing 100084, Peoples R China;

    China Renewable Energy Engn Inst, Dept Engn, Beijing 100120, Peoples R China;

    Anrong Construct Corp, 4 Anrong St, Chengdu 611135, Sichuan, Peoples R China;

  • 收录信息
  • 原文格式 PDF
  • 正文语种 eng
  • 中图分类
  • 关键词

    Cascade landslide dams breach; Emergency management; Back analysis; Soil erosion;

    机译:梯级滑坡大坝破坏;应急管理;反分析;水土流失;